Work Zone Mobility and Safety Program

Transportation Management Plan
Interstate 5 "Boat Section" Rehabilitation

Interstate 5 Boat Section

State of California
Department of Transportation

Caltrans logo

03-SAC-5-KP 36.4/37.8 (PM 22.6/23.5)
EA 03-0A3601

February 25, 2008

Prepared By:

Darren H. Tam, P.E.
TMP Coordinator

Reviewed By:

Joseph W. Horton, P.E.
District 3 TMP Manager

Printable Version [PDF 5.18 MB]
You will need the Adobe Reader to view this PDF.
Contact Information: WorkZoneFeedback@dot.gov


Contents

1.0 Purpose of This Transportation Management Plan

2.0 Project Location

3.0 Project Description

3.1 Background
3.2 Scope of Work

4.0 Transportation Management Plan Summary

5.0 Roles and Responsibilities

5.1 Resident Engineer (RE)
5.2 District Traffic Manager (DTM)
5.3 Project Manager (PM)
5.4 Public Information Officer (PIO)
5.5 Construction Advisory Team (CAT)

6.0 Motorist Information Strategy

6.1 Portable Changeable Message Signs
6.2 Fixed Changeable Message Signs
6.3 Ground Mounted Signs
6.4 Caltrans Highway Information Network
6.5 Highway Advisory Radio
6.6 511 Traveler Information Systems
6.7 www.FixI-5.com Website
6.8 ITS For Traffic Monitoring
6.9 Freight Travel Information

7.0 Incident Management

7.1 Construction Zone Enhanced Enforcement Program
7.2 Access of Emergency Service During Closures
7.3 Freeway Service Patrol
7.4 Caltrans Transportation Management Center (TMC)
7.5 Traffic Surveillance Stations (Loop Detectors and CCTV)

8.0 Construction TMP Strategies

8.1 Lane Closure Chart
8.2 Incentive Clause/Disincentive Clause
8.3 Damage Clause
8.4 A+B Bidding
8.5 Project Coordination

9.0 Stakeholder Coordination

9.1 Team Meeting

10.0 Corridor/Network Management Strategies

10.1 Truck Restriction
10.2 Signal Timing/Coordination Improvements
10.3 TMP Effectiveness Monitoring

11.0 Alternate Route Strategies

11.1 Detours

12.0 Public Information/Public Awareness Campaign

12.1 Brochures and Mailer
12.2 Press Releases
12.3 Emergency Hot-line for the Local Public
12.4 Paid Advertising

13.0 Contractor & Caltrans Traffic Emergency Contingency Plan

13.1 Contractor's Responsibilities
13.2 Contingency Plans
13.3 Communication Plan
13.4 TMC Response Protocol

Contact Information

Attachment A. Construction Advisory Team (CAT)

Attachment B. Detour Sheets