Microsimulation results are highly sensitive to the amount by which the demand exceeds the capacity of the facility, so it is vital that realistic demand forecasts be used in the analysis. The following steps outline a procedure for manually reducing the forecasted demands in the study area to better match the capacity of the facilities feeding the study area.
The analyst should first identify the critical bottlenecks on the facilities feeding the traffic to the boundaries of the microsimulation study area. Bottlenecks are sections of the facilities feeding the model study area that either have capacities less than other sections of the freeway or demands greater than the other sections. These are the locations that will probably be the first ones to experience congested conditions as traffic grows.
These bottlenecks may be located on the boundary of the microsimulation study area, in which case they are identical to the gateway zones on the boundary of the microsimulation model study area. Bottlenecks within the microsimulation model study area can be disregarded since they will be taken into account by the microsimulation model.
Inbound bottlenecks are congested sections feeding traffic to the microsimulation model area. Outbound bottlenecks are congested sections affecting traffic leaving the microsimulation model area. If an outbound bottleneck will probably create future queues that will back up into the microsimulation model study area, then the model study area should be extended outward to include the outbound bottleneck. If the future outbound queues will not back up into the model study area, then these bottlenecks can be safely disregarded (see Figure 19).
If the forecasted hourly demand at a bottleneck (in the inbound direction toward the model) exceeds its capacity, the proportion of the demand that is in excess of the available hourly capacity should be computed:
(Equation 30)
where:
X = proportion of excess demand
D = forecasted demand (veh/h)
C = estimated capacity (veh/h)
The forecasted hourly demands for the off-ramps between the bottleneck and the gateway entering the microsimulation study area should be reduced in proportion to the amount by which the forecasted bottleneck demand exceeds its capacity:
(Equation 31)
where:
Dconst = constrained demand (veh/h) for a downstream off-ramp or exit point
Dunconst = unconstrained demand forecast (veh/h)
X = proportion of excess demand
It is suggested that the off-ramp demand be reduced in proportion to the reduction in demand that can get through the bottleneck, assuming that the amount of reduction in the downstream flows is proportional to the reduction in demand at the bottleneck. If the analyst has superior information (such as an O-D table), then the assumption of proportionality can be overridden by the superior information. The constrained downstream gateway demand is then obtained by summing the constrained bottleneck, off-ramp, and on-ramp volumes between the bottleneck and the gateway to the study area.
Figure 20 illustrates how the proportional reduction procedure would be applied for a single inbound bottleneck that reduces the peak-hour demand that can get through from 5000 veh/h to 4000 veh/h. Since there is an interchange between the bottleneck and the entry gate to the microsimulation study area, the actual reduction is somewhat less (800 veh/h) at the gate.
Starting upstream of the bottleneck, there is an unconstrained demand for 5000 veh/h. Since the bottleneck has a capacity of 4000 veh/h, the downstream capacity constrained demand is reduced from the unconstrained level of 5000 veh/h to 4000 veh/h. Thus, 1000 vehicles are stored at the bottleneck during the peak hour. Since it is assumed that the stored vehicles are intended for downstream destinations in proportion to the exiting volumes at each off-ramp and freeway mainline, the downstream volumes are reduced the same percentage as the percentage reduction at the bottleneck (20 percent). A 20-percent reduction of the off-ramp volume results in a constrained demand of 800 veh/h. The on-ramp volume is unaffected by the upstream bottleneck, so its unconstrained demand is unchanged at 500 veh/h. The demand that enters the microsimulation study area is equal to the constrained demand of 4000 veh/h leaving the bottleneck, minus the 800 veh/h leaving the freeway on the off-ramp, plus 500 veh/h entering the freeway at the on-ramp, which results in a constrained demand of 3700 veh/h.
Table of Contents | List of Tables | List of Figures | Top of Section | Previous Section | Next Section | HOME