Work Zone Mobility and Safety Program
Photo collage: temporary lane closure, road marking installation, cone with mounted warning light, and drum separated work zones.
Office of Operations 21st Century Operations Using 21st Century Technologies

Accelerated Construction

overhead bridge construction

Accelerated construction uses various techniques and technologies to help reduce construction time while enhancing/maintaining safety and quality.

2009 Domestic Scan of Accelerated Construction Practices

In 2009 the American Association of State Highway and Transportation Officials (AASHTO) and FHWA completed a domestic scan of accelerated construction practices for pavement and bridge construction projects. The scan tour visited eight cities in five States and resulted in the identification of accelerated construction best practices in the areas of partnering, design, planning, and contracting strategies, and a set of case studies that demonstrate how projects can be successfully delivered more rapidly.

Accelerated Construction Technology Transfer Program

The Accelerating Construction Technology Transfer (ACTT) Program promotes the use of innovative technologies and techniques to accelerate the construction of major highway projects or corridor improvements using a multidisciplinary team approach.

Accelerated Bridge Construction (ABC)

Prefabricated Bridge Elements and Systems

Prefabricated bridge elements and systems offer bridge designers and contractors significant advantages in terms of construction time, safety, environmental impact, constructability, and cost.

Self-Propelled Modular Transporters (SPMTs)

SPMTs are multi-axle, computer-controlled platform vehicles that can move bridge systems weighing up to several thousand tons with precision to within a fraction of an inch. The vehicles can move in any horizontal direction and also have vertical lift.

Precast Concrete Systems

Precast concrete pavement panels are cast offsite and installed in a short time span when traffic volume is low and lanes can more readily be closed. In high-traffic areas, they can reduce traffic congestion and offer several advantages over traditional cast-in-place construction, including enhancing project safety and mobility, increasing durability, and enabling installation under overpasses with limited height clearances.

  • Utah's Precast Concrete Pavement Experience - In 2009 the Utah DOT (UDOT) completed their first full-scale precast concrete pavement project, replacing several damaged slabs along I-15 near Clearfield and Layton, Utah. UDOT documented a number of lessons learned from the project that could be applied to future projects with precast slab repair.
  • Virginia I-66 Project - This project evaluated two precast concrete pavement technologies, and conventional cast-in-place construction, to replace distressed pavement slabs on a ramp from I-66 to US 50. The Virginia DOT (VDOT) found that precast concrete pavement is a viable alternative to cast-in-place. Using PCPS enabled VDOT to maintain traffic on a busy road by only closing lanes at night. While costs were higher for the PCPS, VDOT expects the overall quality and longevity of the pavement to be better and long-term user impacts to be much less.

Caltrans Long-Life Pavement Rehabilitation Strategies (LLPRS) Program

Caltrans began implementing its Long-Life Pavement Rehabilitation Strategies (LLPRS) program in 1998. While LLPRS is not specifically an accelerated construction strategy, many of the projects that have been completed as part of the program have used a variety of strategies to accelerate construction. The goal of the LLPRS program is to rebuild approximately 2,800 lane-km of high volume urban freeway with pavements that are designed to last more than 30 years with minimal maintenance. The LLPRS Program also addresses the state's need for cost effective approaches for rebuilding the aging pavements in its urban highway network.

You will need the Adobe Acrobat Reader to view the PDFs on this page.

Office of Operations