Figure 32 WisDOT Transportation Management Plan Development Process

Flowchart of WisDOTs transportation management plan development process. This is a flow chart with three decision points. The first is what kind of TMP is required? Type 1 and 2 points to document in DSR. Type 3 points to Project Level Scope, Initial TMP. Type 4 points to Establish TMT. The second decision point with Work zone impacts exceed WisDOT Policies? Yes points to Project Exception Required? No points to Update TMP Strategies, Cost.