Work Zone Mobility and Safety Program

Project 1120-11-03
WIS 26 – Breezewood Lane
US 41
Winnebago County
Traffic Management Plan

The following content was created and provided by the Wisconsin Department of Transportation, is provided here with their permission for reference purposes to users of this FHWA Web site, and is posted in HTML format on this FHWA Web site solely for ease of access by users of screen-reader software.


Download the Printable Version [PDF, 5.9 MB]
PDF files can be viewed with the Acrobat® Reader®.

June 2007
Updated July 2011 (rev #1)

Table of Contents

Executive Summary

Project Description

Existing and Future Conditions

Work Zone Assessment Impacts

Selected Work Zone Impact Management Strategies

Early Improvements to Accommodate Future Interchange and Alternating Interchange Closures
Innovative Construction Contracting
Traffic control devices, positive protection devices, off-peak lane closure, night work, and ramp closure
Traffic Control Meetings and Scheduling
Community Involvement

Incident Management

Tow/freeway service patrol
Deployment of 511
State Traffic Operations Center - STOC
Law Enforcement
Coordinate with Media
Local Detour Routes
Incident/Crisis Communication Plan
Temporary Pullouts for Disabled Vehicles
Temporary Crash Investigation Sites
Special Events

Work Zone Safety Management Strategies

Speed Limit Reduction
Law Enforcement Mitigation Contract
Temporary Traffic Signals
Crash Cushions, Temporary Concrete Barrier, Warning Lights, Traffic Control Provisions, and Traffic Control Devices
Project Onsite Safety Training and Construction Safety Inspector
Street Sweeping
Boat Traffic Control
Temporary In-pavement Reflectors and Glare Screens
Snowplowing
Truck Mounted Attenuators
Community Involvement

Traffic Management Communication Plan

Motorist Information Strategies (MIS) (traveler)

STOC
Portable Changeable Message Signs - PCMS
Electronic Message Signs/ Work Zone Traveler Warning & Information Systems (Intelligent Transportation System)
Highway Advisory Radio-HAR
Availability of Detour Routes
Availability of Alternate Routes
Lane Closure Planning System
Bicycle & Pedestrian Information

TMP Monitoring

List of Attachments

Attachment A – US 41 Traffic Study – Winnebago County Base Year 2005 Traffic Volume Network
Attachment B – US 41 Traffic Study – Winnebago County Year 2035 Traffic Operations Analysis
Attachment C – US 45 Detour Plan
Attachment D – WIS 21 Detour Plan
Attachment E – TRADAS ADT Volumes for July 2006
Attachment F – WIS 76 Detour Plan
Attachment G – CTH K Overpass Detour Plan
Attachment H – Witzel Avenue Overpass Detour Plan
Attachment I – US 41 SB Exit Ramp to WIS 21 Truck Detour Plan
Attachment J – US 41 Winnebago County Construction Schedule
Attachment K – Detail for Construction Access to USH 41


Executive Summary

Enclosed is the Traffic Management Plan (TMP) for the US 41 Winnebago County expansion project. This project is a Type 4 action as determined by Departments DRAFT guidelines for Work Zone Transportation Management Plan established in October 2006 and as currently published in the Facilities Development Manual (FDM) (updated August 2008). This TMP document lays out the project procedures for handling and managing traffic during the construction phase. It addresses overall work zone impacts, selected work zone management strategies, and incident management techniques expected to be implemented during various construction operations.

Because these type plans are considered "living "documents, a final TMP plan will not be complete until the construction plans approach finalization and then there are reporting activities as to the effectiveness of the TMP plan.

The original TMP was developed in June 2007. This July 2011 revision (rev #1) serves as an update to the TMP based on the completed and ongoing project work in Winnebago County.

[ Return to Contents ]

Project Description

The US 41 project is a 17-mile project that plans to reconstruct US 41 from four to six lanes in Winnebago County (see map on page 6). The project extends ½ mile south of the WIS 26 interchange and extends ½ mile north of the Breezewood Lane interchange. The project includes reconstruction of the 9th Avenue, WIS 21, and US 45 interchanges. Moderate interchange improvements will be completed at WIS 44 and WIS 76 interchanges and minor improvements at WIS 26 interchange. Grade separations structures at 20th Avenue and Witzel Avenue will be replaced to meet vertical clearance requirements. New grade separation structures will be added at Lake Butte des Morts Drive and Fountain/Snell roads to provide local road connections near the US 41/45 interchange. The grade separation structures at County Y and CTH GG will also be replaced and the existing overpass structure at County G will be rehabilitated after the US 41 mainline improvements are completed.

The project is currently scheduled in the majors program to be constructed from 2009 to 2016. The project is funded through the Majors program and the schedule is subject to change based on project estimates and available funding. A current Winnebago County schedule is shown in Attachment J. This schedule best takes advantage of funding resources while accommodating alternating interchange closure along US 41. Some of the early projects (2009) were accelerated from the original planned year of 2010 to take advantage of ARRA funding.

The goal of the project is to expand US 41 from 4 to 6 lanes and upgrade the interchanges to handle the projected traffic volumes. Interchanges will be designed with ramp metering calculated into the ramp lengths so meters can be added in the future. The reconstruction of US 41 will provide a much safer facility with better merge/diverge design at the interchanges to handle the future projected traffic.

The proposed construction staging is being determined during the design process. One of the constraints placed on the project is that US 41 remains open to 2 lanes of traffic in each direction during the entire project duration. The reason this constraint has been placed on the project is the hourly volumes for US 41 exceed 1500 vehicles per lane per hour for the entire weekday from 6:00 am to 7:00 pm. Traffic does not reduce down during the daytime that a lane closure can be implemented without causing traffic backups. See Attachment E for traffic volumes. Northeast Region has experienced that by witnessing some of the county maintenance activities and the backup they cause. Nighttime lane closures will be allowed at times for structure demolition, girder placement, and traffic switches. This constraint is necessary to handle the volume of traffic using US 41. We plan to construct the project using various stages to maintain traffic on US 41. US 41 is the only major arterial that crosses the Lake Butte des Morts/Fox River system; alternative routes to handle the large traffic volumes are not present. We propose to close various interchanges and grade separation bridges during construction so we can go in, do the work, do it quickly, get it done, and stay out for a long time in the future. We believe this approach gets the construction done quicker and a better quality product than trying to maintain traffic on cross streets and interchanges extending the work influence for longer periods of time.

Map of the US 41 construction project area near Oshkosh on Lake Winnebago.

[ Return to Contents ]

Existing and Future Conditions

The Department developed the existing traffic data on US 41 in 2000 and updated it in 2005. The Department spent time collecting data on the mainline, ramps, and side roads so it could be used to study the existing traffic conditions and accurately project the future traffic of the facility. Attached is the technical memo entitled US 41 Traffic Study – Winnebago County Base Year 2005 Traffic Volume Network and is attached in Attachment A. The 2005 Annual Average Daily Traffic (AADT) Traffic Volumes on US 41 range from 44,800 on the south end of the project to the highest volume of 68,400 between WIS 21 and US 45. US 41 is used as a tourist route for access to northern Wisconsin so Friday pm and Sunday pm peaks are typical throughout the corridor. During peak travel times Friday night, US 41 northbound travelers experience backups from WIS 44 to US 45. The close interchange spacing in this area combined with the large Friday night peak traffic causes US 41 northbound traffic to be stopped or slowed down to less than 25 mph at peak times. Sunday afternoon return trips also causes backup on US 45 near US 41 as well.

Forecasted traffic projections were completed for years 2015 and 2035 in the technical memo entitled US 41 Traffic Study – Winnebago County Year 2035 Traffic Operations Analysis and are attached in Attachment B. The 2035 Traffic Volumes range from 80,000 to 111,000 within the project limits of WIS 26 to Breezewood Lane with the highest volumes between WIS 21 and US 45. Truck percentages in the corridor are included in Attachment B and average around 14%.

In 2000, the Department completed a crash study of the entire corridor. Five years (1994 – 1998) of crash records were reviewed for US 41 between WIS 26 and Breezewood Lane. Several segments have higher crash rates than statewide average but the northbound US 41 at the WIS 21 interchange and southbound US 41 at the US 45 interchange have significantly higher crash rates. Crash rates may be reduced during construction in the WIS 21 Interchange and US 45 Interchange because the construction staging plans will have those interchanges closed during construction and thus reducing the conflict.

Community and business concerns include addressing the congestion and safety of the corridor. Concerns were high regarding the WIS 21 area along with the Lake Butte des Morts crossing. The Lake Butte des Morts crossing does experience snow drifting issues while the lake is frozen and during low wind speeds from the west or northwest. Maintenance crews have to do continuous plowing and salting operations during those periods when drifting occurs.

The WIS 21 corridor has large commercial development along with high residential development to the west of US 41that experiences traffic congestion during the am and pm peak. The community and business leaders asked the Department to address the congestion issues with the design. WisDOT accelerated the construction of this interchange to one construction season to minimize closures. Construction sequencing is discussed later in this report.

[ Return to Contents ]

Work Zone Assessment Impacts

The designers have given considerable thought to the constraint of fitting a design that will allow two lanes in each direction be maintained during construction. This can be done throughout most of the corridor without much issue. Temporary bypass lanes will need to be constructed at the WIS 21 and US 45 interchanges to allow the work on US 41 mainline to be completed. Temporary bypass lanes along the east side of US 41 were chosen to allow the contractor the most room in which to work and the access materials. Quarries and borrow pits are available to the west of these interchanges.

Lane closures will be allowed at night for material deliveries or structure demolition. Because the existing traffic volumes are large and do not go below 1500 vehicle per hour per lane during daytime, only night time/off peak closures will be allowed. See Attachment E.

The US 45, WIS 21, and WIS 76 interchanges will be closed during construction. Proposed detour routes have been established and are attached in Attachment C, Attachment D and Attachment F. To minimize impacts to the local traffic during the interchange closures, improvements to the local road connections are scheduled prior to the interchange closures including the addition of turn lanes on STH 44, STH 21, and STH 114. The work at the Witzel Avenue Overpass, Lake Butte des Morts Overpass, Fountain/Snell Overpass, Washburn Street, and 9th Avenue Interchange will be done in advance so that when the interchanges are closed, the local traffic has a system that can handle the added capacity. In coordination with the public, the Department committed that no interchange would be fully closed longer than one construction season.

Closures along US 41 will be allowed during off-peak periods for structure demolition and girder placements on select structures along the US 41 Corridor. These closures will be take place in areas where traffic will be able to be routed off and back onto US 41 via interchange ramps adjacent to the structure in order to bypass the work zone. In areas where US 41 traffic is not able to bypass the work zone by using adjacent exit and entrance ramps, a 20-minute rolling closure will be used during off-peak periods or a detour route will be established. The detour routes for the CTH K overpass and Witzel Avenue overpass where traffic cannot be routed off and back on via interchange ramps are shown in Attachment G and Attachment H. In addition, during a brief period trucks will not be able to maneuver through the southbound US 41 exit ramp to WIS 21 due to construction activities on the ramp. A truck detour shown in Attachment I was used to bypass the exit ramp during the widening work.

Pedestrian/bicyclists will be impacted during construction when we close an interchange or overpass. Pedestrians/bicyclists will have to plan alternate routes around the construction.

The NE Region has currently scheduled other WisDOT projects to avoid conflicts while the US 41 project is under construction. Currently, resurfacing projects on WIS 76 are programmed in advanced of US 41 work so that WIS 76 can be used as a relief route. No work is anticipated to be needed on the detour routes for US 45, WIS 21, and WIS 76 interchange closures. While side roads are under construction, various strategies will be used to get the work completed and maintain traffic on US 41. Strategies being considered are to allow short duration off peak lane closures, long-term shoulder closures, redirecting traffic onto ramps for off peak periods, intermediate completion dates for various aspects of work with potential/disincentive clauses.

NE Region will coordinate schedule with local community leaders, emergency services, schools, and local businesses so they can plan early the construction and necessary changes that impact them.

[ Return to Contents ]

Selected Work Zone Impact Management Strategies

Numerous work zone traffic control strategies and devices will be considered in the upcoming projects on US 41. Some of the devices presently being considered are changeable message signs, fixed message signs, and variable speed message signs. Several strategies being considered are enhanced enforcement contracts, crash investigation sites, and temporary emergency pullouts.

Early Improvements to Accommodate Future Interchange and Alternating Interchange Closures

A construction staging and packaging schedule was developed to best minimize impact to the traffic along the Winnebago County section of US 41, minimize use of detours, and streamline construction operations.

One strategy was to alternate interchange closures and complete improvements to various interchanges early to accommodate alternating major interchange closures. From 9th Avenue up to Breezewood Lane interchange closure requirements were set as follows:

  • 9th Avenue closure – WIS 44 and WIS 21 open
  • WIS 21 closure – 9th Ave, Witzel Ave, and US 45 open
  • US 45 closure – WIS 21 and WIS 76 open
  • WIS 76 closure – US 45 and Breezewood Lane open
  • Breezewood Lane closure – WIS 76 open

From south to north, various interchange and local road improvements were also planned to accommodate alternating interchange closures:

  • US 41 SB Exit Ramp to WIS 21 (2009) – Project 1120-11-74 – Construct SB ramp widening to WIS 21 in 2009 so improvements are in place during the Witzel Avenue Overpass and 9th Avenue Interchange closures in (2010) and (2011), respectfully.
  • WIS 26 (2009) - Project 1120-10-76 – Construct crash investigation sites so they are in place during 9th Avenue interchange closure (2011) and US 41 mainline reconstruction.
  • WIS 44 (2009) – Project 1120-10-75 – Construct crash investigation site and turn lanes so improvements are in place during the 9th Avenue interchange closure (2011) and during US 41 mainline reconstruction.
  • WIS 114 (2009) – Project 1120-09-73 – Construct turn lanes and signal improvements at WIS 114 to accommodate traffic during closure of the Breezewood Lane interchange (2011).
  • WIS 21 (2010) – Project 1120-10-73 – Lengthen existing left turn lane at WIS 21 onto Oakwood Road so improvements are in place during the 9th Avenue interchange closure (2011) and during US 41 mainline reconstruction.
  • WIS 76 (2010) – Project 1120-09-75 – Construct ultimate ramp improvements to allow WIS 76 to remain open during closure of the US 45 interchange (2011).

A second strategy was to develop separate TMP contracts to accelerate portions of mainline construction:

  • US 41 North (Snell Road to Breezewood Lane) – Project 1120-09-83 – construct widening and bridges along northbound US 41 mainline to accommodate staging and scheduling of the ultimate mainline improvements under Project 1120-09-71.

A third staging strategy was to complete local road improvements prior to adjacent interchange reconstruction and closures to accommodate local traffic circulation around the interchanges and to also allow for acceleration of interchange reconstruction schedules:

  • CTH K Overpass (2010) – Project 1120-10-71 – reconstruct overpass to allow for local traffic circulation during 9th Avenue interchange closure (2011).
  • Witzel Avenue Overpass (2010) – Project 1120-11-71 – reconstruct overpass and associated local road improvements to allow for local traffic circulation during 9th Avenue (2011) and WIS 21 interchange closures (2012).
  • Snell Road Overpass (2010) – Project 1120-11-72 - construct new overpass north of proposed US 45 system interchange to allow for local traffic circulation during the US 45 interchange closure (2011).
  • US 41 SB Widening across Lake Butte des Morts and Lake Butte des Morts Drive (2010) – Project 1120-11-74 and US 45/Fernau Avenue/Stillman Drive – construct overpass and local roads in the area of the US 45 interchange to allow for local circulation during closure of the US 45 interchange (2011). Project also include advanced lake fill within Lake Butte Des Morts and advance fill areas and construction of bridges in off-alignment areas within the US 45 interchange. Advance placement of lake fill and construction in off-alignment areas in the US 45 interchange will allow for construction of 1120-11-83 (2011-2012) to be accelerated and will minimize closure time of the US 45 interchange.
  • Green Valley Road and Dixie Road (2010) – Project 1120-09-79 – Overlay local roads to accommodate heavy truck traffic from Neenah business areas during closure of the Breezewood Lane interchange (2011).

Innovative Construction Contracting

Unique contracting will be considered for US 41 that can speed up contracting and lessen the impacts to the travelling public. For example, A+B bidding and lane rental contracts will be considered but ultimately were not implemented on the corridor.

The methods used in the US 41 corridor to expedite contracts are Incentive/Disincentive clauses and interim completion dates with liquidated damages. These two methods are used in order to complete projects in a timely manner and to develop staging scenarios which closely tie work between project LETs while accommodating two lanes of traffic on US 41 during peak travel periods.

Almost all projects in the US 41 corridor have interim liquidated damages associated with interim completion dates to meet schedule, critical opening and closure dates, and other schedule requirements which allow the corridor construction to proceed in a timely and orderly manner. The liquidated damages used on the Winnebago County projects ranges from $150 - $5,000 and the amount is project dependent. Approval and coordination of the liquidated damage amounts was review and approved by Central Office prior to each PS&E.

Off-peak closures and night work will be implemented to minimize user delay. Interim liquidated damages will be implemented to ensure the contractor re-opens lanes to traffic by the time required. Off-peak closure periods and interim liquidated damages for failing to open lanes to traffic vary based upon project location. The interim liquidated damages for failing to open a lane traffic are shown below. The closure periods are discussed later in this report.

  • Local road projects and projects over/under US 41 constructed in 2009/2010 used interim liquidated damages of $2000 for the initial penalty and an additional $2000 for each hour or portion thereof after the initial failure to open the lane.
  • Projects on mainline US 41 constructed in 2010 and later used interim liquidated damages of $2000 for the initial penalty and an additional $2000 for each 15-minute period or portion thereof after the initial failure to open the lane.
  • Project 1120-11-73 - US 45, Fernau Avenue, Snell Road, & Stillman Drive used liquidated damages of $1000 for the initial penalty and an additional $1000 per hour or portion thereof after the initial failure to open the lane on US 45.
  • Project 1120-10-75 - WIS 26 – WIS 21 (WIS 44 Left Turn Lanes) used liquidated damages of $150 per hour per ramp (US 41 Ramps to WIS 44) for failing tore-open the ramp to traffic.

Projects (listed from south to north) within the US 41 corridor which used Incentive/Disincentive clauses in addition to the liquidated damages are described below:

  • US 41; WIS 26 – WIS 44 – Project 1120-10-80 – Interim completion on US 41 mainline to allow traffic switches to occur with the adjacent Project 1120-10-72 and 1120-10-73.
  • US 41; WIS 44 – Witzel Avenue – Project 1120-10-72 and 9th Avenue Interchange – Project 1120-10-73 – Interim completion on US 41 mainline to allow traffic switches to occur with the adjacent Project 1120-10-80.
  • Witzel Avenue Interchange. – Project 1120-11-71 – complete work prior to Projects 1120-10-72 and 1120-10-73 to eliminate or minimize overlapping work zones.
  • US 41; WIS 21 Interchange & Lake Butte des Morts Crossing – Project 1120-11-75 – interim completion on US 41 mainline to allow traffic switches to occur with the adjacent Project 1120-11-83.
  • US 41; US 45 Interchange – Project 1120-11-83 – interim completion on US 41 mainline to allow traffic switches to occur with the adjacent Project 1120-11-75 and Project 1120-09-71.
  • WIS 76 interchange - Project 1120-09-75 –complete work prior to Project 1120-09-83 to eliminate overlapping work zones.
  • US 41 North TMP/Breezewood Lane interchange – Project 1120-09-83 – interim completion on US 41 mainline widening to allow US 41 mainline ultimate reconstruction work to begin under Project 1120-09-71.
  • US 41; US 45 – Breezewood Lane - Project 1120-09-71 – Interim completion on US 41 mainline to allow traffic switches to occur with the adjacent Project 1120-11-83.

Traffic control devices, positive protection devices, off-peak lane closure, night work, and ramp closure

The numerous strategies listed above will be considered in final design. The strategies to be used in construction depend on the type of work, duration of the work, and the impacts to the travelling public. Traffic control devices will be implemented in accordance with MUTCD and WisDOT standards throughout the project.

Off-peak closure periods have been approved by the NER Traffic Section and will be implemented on the specified US 41 Winnebago County projects as shown in Table 1.

Table 1: US 41 Corridor Off-Peak Closure Periods
Project No. Project Name Off-Peak Closure Periods
*1120-11-72 Fountain Avenue / Snell Road Overpass 8:00 pm – 5:00 am Sunday night – Friday morning
1120-11-73 US 45, Fernau Ave., Snell Rd, & Stillman Drive 9:00 am – 2:00 pm & 8:00 pm – 5:00 am (US 45)
*1120-11-71 Witzel Ave. Overpass, Washburn St., Koeller St., & Rath Ln. 9:00 pm – 5:00 am Sunday night – Friday morning
*1120-11-74 Lake Butte des Morts Drive Overpass & US 41 Southbound Grading Across Lake Butte des Morts 8:00 pm – 5:00 am Sunday night – Friday morning
*1120-10-71 County K Overpass 9:00 pm – 5:00 am Sunday night – Friday morning
1120-09-75 US 45 – Breezewood Lane
(WIS 76 Ramps)
7:00 pm – 6:00 am Sunday night – Friday morning
*1120-09-83 US 45 – Breezewood Lane US 41 Mainline Widening and Breezewood Interchange 7:00 pm – 5:00 am Sunday night – Friday morning; 10:00 pm – 7:00 am Friday night – Saturday morning and 6:00 pm – 8:00 am Saturday night – Sunday morning
*1120-11-83 WIS 21 – US 45 9:00 pm – 5:00 am Sunday night – Friday morning; 10:00 pm – 7:00 am Friday night – Saturday morning and 6:00 pm – 8:00 am Saturday night – Sunday morning
1120-10-72 WIS 26 – WIS 21 (9th Avenue Interchange) 7:00 pm – 5:00 am Sunday night – Friday morning; 10:00 pm – 7:00 am Friday night – Saturday morning and 6:00 pm – 8:00 am Saturday night – Sunday morning
1120-10-73 WIS 26 – WIS 21 (WIS 44 – Witzel Avenue) 7:00 pm – 5:00 am Sunday night – Friday morning; 10:00 pm – 7:00 am Friday night – Saturday morning and 6:00 pm – 8:00 am Saturday night – Sunday morning
1120-10-80 WIS 26 – WIS 44 7:00 pm – 5:00 am Sunday night – Friday morning; 10:00 pm – 7:00 am Friday night – Saturday morning and 6:00 pm – 8:00 am Saturday night – Sunday morning
1120-09-71 US 45 – Breezewood Lane 7:00 pm – 5:00 am Sunday night – Friday morning; 10:00 pm – 7:00 am Friday night – Saturday morning and 6:00 pm – 8:00 am Saturday night – Sunday morning
*1120-11-75 WIS 21 Interchange & Lake Butte des Morts Crossing 9:00 pm – 5:00 am Sunday night – Friday morning; 10:00 pm – 7:00 am Friday night – Saturday morning and 6:00 pm – 8:00 am Saturday night – Sunday morning
1120-10-75 WIS 26 – WIS 21 One Closure 6:00 pm – 6:00 am
One Closure 9:00 am – 3:00 pm
*20-minute rolling closures will be used in off-peak periods on US 41 projects for bridge removals and girder placement for locations where traffic cannot be routed off and back on via interchange ramps.

Failure to open lanes to traffic after the allowed closure periods will result in assessment of interim liquidated damages. These are described in the Innovative Construction Contracting section of this report.

Traffic Control Meetings and Scheduling

All contracts will require the contractor to submit a detailed proposed 2-week look-ahead traffic closure schedule to the engineer. This will allow active management of closure dates, closure durations, work causing the closure and detours to be used, emergency contacts, and other traffic management information. Traffic management meetings will also be scheduled as required with local agencies, project stakeholders, owner managers, owner engineers, contractors, document control and construction engineering personnel together to discuss traffic staging, closures and general impacts. Upon obtaining feedback from the meeting changes will be made, as required, to the traffic control plan.

The US 41 corridor team has designated a corridor Traffic Engineer, Brian Chlopek, to oversee all traffic control and traffic management coordination on all US 41 contracts.

Community Involvement

Work zone impacts have and will be addressed through community involvement prior to the project. Impacts and schedules will need to be communicated with the local officials and business leaders prior to the project so that they can plan accordingly. Businesses directly affected by construction will be allowed to provide temporary business signing during construction to help direct customers to their place of business. The temporary signing will follow the NE Region policy that is already in place.

[ Return to Contents ]

Incident Management

Tow/freeway service patrol

Tow and freeway service patrols will be considered along US 41 corridor during construction activities. As part of a traffic mitigation program called Freeway Service Team (FST), the department has contracted with a private towing vendor to patrol parts of US 41 during peak hours, holidays and special events from 2011 through July 2013. To improve safety and minimize delay, contact 911 immediately for breakdowns or incidents in or near the construction work zone. FST will be dispatched directly to the scene to aid the vehicles that need to be removed.

Deployment of 511

511 has been deployed statewide and has been utilized to inform motorists on construction activities and traffic conditions along the US 41 corridor.

State Traffic Operations Center - STOC

The STOC will be used as the primary contact for any infrastructure repair needs. The STOC will as be utilized to either monitor or operate field devices deployed as part of the major projects.

Law Enforcement

The state patrol and other law enforcement agencies may be used for extra-ordinary enforcement purposes. The level of effort will need to be determined as the design of the project increases. Coordination will be completed with state patrol on a project by project basis.

Coordinate with Media

Coordination with the media will be critical to a successful project. Information such as lane closures times and locations, detour route changes and other planned events that affect traffic will be shared with the media in various methods. The current lane closure form will be utilized as ramp, lane or shoulder closures are needed. A US 41 corridor website (http://www.us41wisconsin.gov/) and social media such as Facebook and Twitter are used to provide traffic and project updates to the media and public.

Local Detour Routes

No local detour routes are planned. While work is taking place on the local routes, local municipalities may incorporate their own detours for those affected routes.

Incident/Crisis Communication Plan

An Incident/Crisis Communication Plan for the US 41 corridor in the Northeast Region has been developed to ensure accurate, consistent and timely communications; eliminate or minimize confusion; and to maintain credible relations with public officials, emergency response providers, the media, the public and all mutually identified stakeholders in the event of an incident or Emergency. The Incident/Crisis Communication Plan was last updated in June 2011 and is currently being maintained by the US 41 Traffic Engineer.

In addition, the Winnebago County Freeway Incident Management team meets once per month to discuss traffic incident response procedures. WisDOT has held crisis management workshops with local emergency response teams. A workshop was held in January 2010 and 2011. During the workshops, the US 41 staff and local response teams reviewed the US 41 corridor by segment in each stage to determine the approach to be taken during an incident. Future workshops will be scheduled as the work zone changes.

Temporary Pullouts for Disabled Vehicles

Temporary pullouts for disabled vehicles have been constructed in the following locations:

  • Two temporary pullouts constructed between WIS 21 and US 45 under Project 1120-11-75
  • One temporary pullout constructed between WIS 21 and US 45 under Project 1120-11-74
  • One temporary pullout constructed between US 45 and WIS 76 under Project 1120-11-83,
  • Two temporary pullouts constructed between WIS 76 and Breezewood Lane under Project 1120-09-83 will accommodate disabled vehicles during mainline reconstruction under Project 1120-09-71.

Crash investigation sites will also be constructed on the off-ramps to many of the interchanges.

Temporary Crash Investigation Sites

If any temporary crash investigation sites are constructed they are expected to be located where permanent ones will be placed as part of the projects.

Crash investigation sites constructed early as part of Project 1120-10-76 at WIS 26, Project 1120-10-75 at WIS 44, and as part of the Project 1120-09-75, WIS 76 will allow them to be utilized during construction. Other crash investigation sites will be constructed as part of the ultimate configuration of the 9th Avenue, WIS 21,US 45, and Breezewood Lane interchanges.

Special Events

Certain special events affect US 41 that need to be considered and addressed through the project final design and special provisions. Green Bay Packer home games, Experimental Aircraft Association (EAA) Fly-in, Rock Fest, and Country USA country music festival are events that need to be addressed in final plans. A corridor-wide specification has been developed to incorporate into all Winnebago County contracts to notify the contractor of the working restrictions for these events. Coordination with law enforcement will occur prior to and during construction periods which overlap with these special events.

[ Return to Contents ]

Work Zone Safety Management Strategies

Speed Limit Reduction

Regulatory speed limit will be reduced to 55 mph when traffic control requires counter-directional traffic. The regulatory speed limits will also be reduced to 55 mph when workers are present and working adjacent to the through lane of traffic. At all other times the regulatory speed limit will be 65mph. Any hazards throughout the project should be identified with a warning sign with an appropriate advisory speed plaque.

Law Enforcement Mitigation Contract

The state patrol is being used for extra-ordinary enforcement purposes. The state patrol is typically on site to provide additional enforcement for rolling roadblocks, during girder placement, when implementing lane closures and setting barrier wall, and during traffic switches.

Temporary Traffic Signals

Temporary Traffic Signals were considered as a possible measure during design. No temporary signals were required on the corridor.

Crash Cushions, Temporary Concrete Barrier, Warning Lights, Traffic Control Provisions, and Traffic Control Devices

These items will be considered for use in the appropriate place and installation per MUTCD and WisDOT standards. Corridor specifications have been implemented for storing materials and equipment outside of the clear zone areas and for protecting bridge piers or hazards within the clear zone to ensure roadside safety during construction.

Special details and special provisions will be developed based on each individual project location to allow construction traffic to safely exit and enter live traffic. Construction of temporary access may be required in various locations. Access into the work zones from US 41 during peak periods is subject to approval by the engineer and has been accomplished using acceleration entrance lanes (Attachment K). Exiting from the work zone onto US 41 will only be allowed using a lane closure and construction traffic must run out of the closed lane. Once construction traffic is within a lane closure, construction traffic must come to within 10 mph of posted speed before re-entering the live US 41 lane.

Project Onsite Safety Training and Construction Safety Inspector

An Owner Controlled Insurance Plan (OCIP) with a major safety component has been implemented on US 41. All on-site staff, contractors, subcontractors working on the project participate in mandatory safety training and monitoring.

Street Sweeping

Street sweeping with an appropriate level of hours will be used on contracts to keep pavement clear of debris and dirt and maintain roadway safety.

Boat Traffic Control

Traffic control details and appropriate warning devices will be used during the Lake Butte Des Morts lake fill and bridge replacement projects in order to safely maintain boat navigation on Lake Buttes Des Morts. Coordination will occur as required with Wisconsin DNR.

Temporary In-pavement Reflectors and Glare Screens

In-pavement reflectors and temporary glare screens on temporary concrete barrier will be used during stage construction in bypass and crossover areas to aid in keeping traffic in their designated lanes and maintain safety due to headlight glare.

Snowplowing

A corridor wide specification will be developed and placed in contracts to let the contractor know who will be responsible to perform snow removal operations for freeway and local roads that are open to through traffic during construction.

Truck Mounted Attenuators

Truck Mounted Attenuator (TMA) and operator, if required, and the appropriate number of hours will be used on US 41 mainline projects for use during operations which are directly next to live lanes of traffic which have limited mobility, limited ingress/regress, confined space, or as directed by the engineer.

Community Involvement

In March 2004, WisDOT met with City of Oshkosh local officials to investigate if any local arterials needed modifications or upgrades prior to the work on US 41. The local arterials that will be used during US 41 construction are already 4 lane arterials. DOT asked if turn lanes or signal timing adjustments needed to be done. The City did not think any turn lanes adjustments are needed and signal timings could be adjusted at time of construction if necessary.

WisDOT continued to meet with the local officials throughout design through the use of local official meetings and public information meetings approximately every six months. During construction progress meetings are held at the local field office and local officials participate in meetings on an as-needed basis.

[ Return to Contents ]

Traffic Management Communication Plan

This plan actually starts during the public outreach part of the project, where we meet with local officials, businesses and citizens. We communicate about the project and receive feedback regarding issues, needs and concerns. This information is used in developing the traffic management communication plan.

Communication is targeted locally on commuters, area businesses and safety agencies. Regional and interstate communication focuses on tourists, trucking firms, and businesses.

There are a number of goals to be achieved with this communication. They include communicating the necessity for the work, the benefits once the work is completed, the project schedule, impacts and access plan and how to deal or cope with it.

Project updates and status will be issued frequently – hourly if necessary. Alternate routes will be suggested as appropriate. Safety messages will also be provided, including urging the public to slow down and be patient.

This information will be communicated to a number of venues. Included will be brochures and posters distributed throughout the corridor and both up and down state. Print and electronic media will be brought in as partners in the outreach. WisDOT will also provide updated information through its web site, e-mail, conventional mail, public service announcements, paid advertising (if needed) and public meetings.

The USH 41 corridor will include construction of roundabouts. Throughout design and construction, WisDOT has and will continue to complete outreach with a focus on educating and training the public about navigating through roundabouts. Tools used included rendering of roundabouts, computer simulations, distribution of educational materials, and holding workshops at local service organizations approximately two times per year. The outreach focuses on all modes of transportation including vehicular traffic, truck traffic, pedestrians, and bicyclists.

[ Return to Contents ]

Motorist Information Strategies (MIS) (traveler)

STOC

The STOC will be used as the primary contact for any infrastructure repair needs. The STOC will be utilized to either monitor or operate field devices, which will be used in part to provide traveler information.

Portable Changeable Message Signs - PCMS

PCMS will be utilized throughout the project. The use will be for incident management, notification of lane, shoulder, and/or ramp closures, for truck traffic entering/exiting the work zone, and other traveler information necessary. A corridor-wide specification has been implemented to obtain USH 41 Traffic Engineer approval prior to implementing the PCM.

Electronic Message Signs/ Work Zone Traveler Warning & Information Systems (Intelligent Transportation System)

Permanent message boards are planned to be installed as part of the project. These signs could be utilized once installed if construction is ongoing downstream. A Portable Intelligent Transportation System (ITS) was implemented as part of the Winnebago County work in 2010 which makes early use of the corridor ITS during construction. A corridor wide specification is placed is each contract to notify the contractors of the portage ITS on the mainline US 41 projects. Message boards are in place on eastbound STH 26 for traffic destined for northbound USH 41 and on northbound USH 41 south of STH 26. A message board will also be installed for southbound USH 41 just north of STH 76. Temporary cameras (CCTV) have also been installed throughout the corridor to aid with traffic management during construction.

Highway Advisory Radio-HAR

HAR is not expected to be used as part of this project. The need for HAR has been diminished with the development of the 511 traveler information system.

Availability of Detour Routes

There are no readily available detour routes for US 41 along this segment of highway. An emergency detour route can be used, but it will not handle an extended period of high volumes of traffic directed to it.

Availability of Alternate Routes

Two alternate routes around the Lake Butte des Morts are signed. Other alternate routes are identified in the Green Bay/Fox Cities/Oshkosh Alternate Route Plan Guide, but are not signed. County highway departments have equipment available to sign an alternate route due to an incident on the freeway.

Alternate routes will not be signed through the City of Oshkosh but some traffic may choose to find alternate routes on their own in order to avoid the US 41 work zones. WisDOT completed a recent analysis of traffic that is self-diverting from USH 41 during the 2011 construction season. South of the Lake Butte Des Morts Causeway there is about a 38% drop in ADT. North of the Lake Butte Des Morts Causeway there is no diversion occurring with a slight increase in ADT. The City of Oshkosh has not reported any issues on the local or state highway system through the city due to the diversion. See table below:

SNELL ROAD (NORTH OF US 45)
DATE NB ADT SB ADT TOTAL ADT NOTES PERCENT CHANGE IN ADT DURING CONSTRUCTION
3/4/09 24625 24766 49391
3/2/11 24402 24872 49274 Prior to US 45 closure 0%
5/6/09 26936 26691 53627

5/11/2011

30460 27147 57607 After US 45 closure -7%
6/3/09 27190 26832 54022
6/1/11 28574 27906 56480 After US 45 closure -5%


9th AVENUE / STH 21
DATE NB ADT SB ADT TOTAL ADT NOTES PERCENT CHANGE IN ADT DURING CONSTRUCTION

2/18/2009

23096 23067 46164 South of WIS 21

2/16/2011

23305 21554 44859 North of 9th Ave 3%

5/27/2009

29521 30219 59740 South of WIS 21

5/25/2011

17056 20177 37233 North of 9th Ave 38%
6/3/09 30506 30536 61042 South of WIS 21
6/1/11 16677 21132 37809 North of 9th Ave 38%

Lane Closure Planning System

The Department has developed a Lane Closure Planning System on a statewide basis. The Lane Closure Planning System is utilized to track and inform motorists of construction operations so that they can plan ahead to anticipate or avoid delays.

Bicycle & Pedestrian Information

Bicycle and pedestrian information will be disseminated through the local officials and concerned groups as part of the regions public outreach for the projects. Alternate routes or closure of bicycle and pedestrian routes will occur on project by project basis. The Wiouwash Trail through the US 45 interchange will be maintained during construction and will be routed on the Lake Buttes Des Morts Drive overpass to cross US 41.

TMP Monitoring

Traffic Management Plan monitoring will be completed by the US 41 corridor Traffic Engineer, Brian Chlopek, who will oversee all traffic control and traffic management coordination on all US 41 contracts.

This July 2011 update serves as an update to the US 41 corridor TMP in Winnebago County. An Evaluation Report will be developed upon completion of construction to document lessons learned and provide recommendations on how to improve the WisDOT TMP process and/or modify the guidelines. The reports will address the following:

  • A statement reflecting the usefulness of the TMP
  • Updates necessary to correct oversights in the TMP
  • Modifications made to the original plan and their level of success
  • Public reaction to the TMP
  • The maximum and average delay time encountered (e.g., average queues, slowdowns) during construction, and history of delay (if any) over the duration of the project
  • If there were any peak traffic periods exceeding the predicted
  • Frequency of legitimate complaints and the nature of those complaints
  • Types and numbers of crashes that occurred during construction
  • Types and numbers of safety service patrols incidents
  • The level of success and performance log for each strategy of the TMP implemented
  • Recommended or suggested improvements or changes for similar future projects

Contact Information:

Tom Buchholz, P.E.
Wisconsin Department of Transportation
944 Vanderperren Way
Green Bay, WI 54304
920-492-2227

View Attachments