Appendix A: Post Course Assessment
Post Course Assessment
Place a checkmark in the box next to the one correct answer for each question.
- What are the primary components of the Work Zone Safety and Mobility Rule?
- Work zone safety and mobility policy
- Processes and procedures to implement work zone policy
- Project-level procedures to assess and manage impacts on individual projects
- Use of law enforcement in work zones
A and B
B and C
A and D
A, B, and C
All of the above
- The Work Zone Safety and Mobility Rule requires that a Transportation Management Plan (TMP) be developed for ? (choose the best answer)
Projects with a budget of more than $100 million
Interstate projects only
Federal-aid projects
All projects with lane closures
- Which component(s) of the TMP is/are always required?
- Temporary Traffic Control Plan
- Transportation Operations Plan
- Public Information and Outreach Plan
- Incident Management Plan
A and C
A only
B only
A, B, and C
All of the above
- A significant project is one that has the potential to cause a relatively high level of disruption.
The above statement is true
The above statement is false
- Which of the following is/are a required component(s) of the TMP for significant projects?
- Temporary Traffic Control Plan
- Transportation Operations Plan
- Public Information and Outreach Plan
- Incident Management Plan
A only
B and C
A, B, and C
B, C, and D
All of the above
- FHWA requires a specific format for all TMPs.
The above statement is true
The above statement is false
- The TMP should always be paid for:
As a single pay item in the construction contract
As an incidental item and not paid for separately
As a separate pay item for every strategy
None of the above
- When in TMP development should coordination with key stakeholders occur?
During the preliminary engineering phase
During the design phase
During the construction phase
All of the above
- Traffic analysis tools are used to:
- Quantify corridor delay resulting from capacity decreases in work zones
- Support tradeoff analyses between construction costs and delay costs
- Identify safety impacts of alternative project phasing plans
- Assess travel demand measures and other delay mitigation strategies
A and B
A and C
A, B, and C
A, B, and D
All of the above
- When should the work zone impact assessment process start?
During early scoping stages of the project
During preliminary project design stages
During final project design stages
None of the above
- During construction, pedestrian and bicycle access should be maintained to a similar level as that existing prior to construction.
The above statement is true
The above statement is false
- Which among the following is a Transportation Operations strategy?
- Alternate construction phasing/staging
- Transit incentives
- Signal timing/coordination improvements
- Press releases about the project
A only
A and C
B and C
All of the above
- Public information provided during a project should always be:
A. Timely, Low-Cost, and Consistent
B. Accurate, Timely, and Consistent
C. Accurate, Consistent, and Web-Based
D. Accurate, Consistent, and Real-time
- Who should designate a trained, responsible person at the project level to implement and monitor TMP elements?
State Agency only
Contractor only
Both State Agency and Contractor
None of the above
- Which among the following is a benefit of TMP monitoring during construction?
- A TMP is a static document and should not be monitored during construction.
- Determine if TMPs on future similar projects are not needed.
- Protect against litigation
- Determine elements to include/correct in future TMPs
A and B
B and C
C and D
A, B, C, and D
- A contractor can make changes to a TMP on its own.
The above Statement is true
The above Statement is false
This is the end of the assessment.
Please turn to page 211 of the Participant Workbook for the answer key.
previous | next