Work Zone Mobility and Safety Program

Contractual Challenges of Successful Smart Workzones

slide 1: Contractual Challenges of Successful Smart Workzones

Ralph Adair

Minnesota Department of Transportation Regional Transportation Management Center

slide notes:

None




slide 2: Why Do it ?

A congested freeway.

slide notes:

Is it really worth it?

Late 90's early 2000 systems in the way




slide 3: Several reasons

  • Provide Delay Information To Motorists
  • Potential for Diversion
  • Perception Tracking Survey Results
  • FHWA Guideance
A work zone with a closed segment of roadway.

slide notes:

None




slide 4: Why Integrate with RTMC?

  • Proven Method of Calculating Travel Times
  • Reduced Costs
    • Utilize existing 150+ DMS
    • Utilize detection outside of work zone
      • Currently have 400 miles of freeway instrumented with loop detection
      • Future detection will utilize more Microwave sensors which may allow detection within work zones
  • Existing information flow

slide notes:

Blessing and a curse having a large operating system




slide 5: Integration into existing systems

  • Traveler Information Website
  • Travel Times Signs
An example of a traffic heat map and a photo of a freeway with free moving traffic and a travel time advisory message on an overhead dynmaic message sign.

slide notes:

None




slide 6: Travel Time Messages - Actionability

Q71b. How often, if at all, do you take an ALTERNATE ROUTE because a travel time message on an overhead electronic message sign showed a longer time than your usual time for the trip?

  • Among those drivers who make a route decision based on a travel time message, nearly 6 in 10 chose to take an alternate route at least some of the time.

Results from a perception tracking survey summarize the finding that, during 2011 and 2012, nearly 6 in 10 respondents would sometimes or almost always take an alternate route at least some of the time. Survey base included 398 participants in 2012 and 393 participants in 2011.

slide notes:

None




slide 7: Contracting options

  • Traditional sub-contract to main project
  • Stand alone for a single construction project
  • Stand alone for multiple construction projects

slide notes:

Assume DOT doesn't purchase systems,
Really 4 ways of doing temp systems
4th is concept for us, haven't done it.




slide 8: Detection Trailer

  • Microwave Sensor
  • Camera
  • Wireless Modem
  • Solar Power
  • Occasionally DMS
Portable solar powered traffic camera.

slide notes:

Equipment used is really consistent thru out the methods
And a controllable DMS




slide 9: Method #1 - Include in Main Construction

  • Easy
  • Fits Contracting Process
  • Typically lump sum

slide notes:

It's Easy
It's what we do
Contract people like this method
Typically lump sum bid item




slide 10: Issues

  • Low Priority
  • Timing Startup time even more important with existing system integration
  • Lack of communications about traffic switches
  • Inadequate detection methods
    • Increased detection spacing
    • Probe data
  • Cost

slide notes:

Picture is worth a thousand words
ITS is low priority for prime because of dollars
Timing is problematic at best
Need systems online at start of lane restrictions, Integration takes time
Deductions can't give drivers back the time they lost
Very inflexible, and limited control
Cost was really the straw




slide 11: Costs when Included in Main Project

  • I-35E – From CR 96 to I-35
    • 8 miles
    • $250,000
  • I-694 – From Hwy 61 to Hwy 5
    • 7.5 miles
    • $185,000

slide notes:

None




slide 12: Method #2 - Stand alone per Project

  • Allows ITS Focus
  • More Control for Contractor
  • More Direct oversight by DOT
  • Better Timeline

slide notes:

Prime Contractor is focused on ITS
Better control for both Contractor and DOT
Leads to better timeline, get started early
Which helps Integration




slide 13: Issues with Method 2

Still Can't address rapidly changing Construction Program
Susceptible to multiple Integration needs
Adds contract management needs
Cost

slide notes:

Lead time is sometimes more than the project
i.e. canned project on the shelf moved up




slide 14: Project example

  • Separate Project, I-494
    • 6 miles of system
    • $262,300
    • 2 years of system
    • Includes a camera site
Diagram of a mainline project area with major cross-streets indicated.

slide notes:

Our experience was very good with this project
Flexible,
Moved a camera to location to cover unanticipated loss.
Provided critical view of incident the following week.




slide 15: Another example

Another example

  • I-94 Between Twin Cities and St. Cloud
    • $187,100
    • 24 miles of system
    • Mix of Existing rural spaced Detection and DMS's
    • 11 Temporary DMS
    • 21 Temporary Detection trailers

slide notes:

Hasn't happened yet,
Very short duration,
Completed by mid summer




slide 16: Rural example

  • Duluth MN
    • 70 mile Detour
    • 4 NB 3 SB signs
    • 12 sensors
    • Best value
    • 1 season in length
    • $320,000
  • Despite inaccuracies, system was well received
Traffic barrels delineate a stretch of newly laid asphalt in a rural work zone.

slide notes:

Left detection up to contractor
Significant issues with accuracy
MN/DOT and Contractor each held some responsibility
Perception tracking and survey results were interesting




slide 17: Method #3 – Stand alone for Multiple Projects

  • All the benefits of stand alone ITS project
  • Increased Flexibility
  • Plus reduced
    • Management costs
    • Configuration and integration time

slide notes:

None




slide 18: Metro Wide Project - SP 8825-465

  • Provide one prototype trailer.
  • SP 0285-65 on I-694 from Hwy 252 to I-35W. 
    • Provide 16 trailers.
  • SP 1982-161 on I-35E from I-35 south split to Cliff Rd. 
    • Provide 8 trailers.
  • SP 2776-103 Hwy 169 River Bridge. 
    • Provide 18 trailers plus 3 PCMS.
  • SP 7080-51, 7080-50 on I-35 from District Border to I-35 south split. 
    • Provide 30 trailers which includes 3 w/ cameras plus 3 PCMS.
  • Actual bid price $569,141 

slide notes:

Total Projected Cost - $640,750
Was plausibly $800,000 bid based on past rentals




slide 19: Looking Forward - Method 5

  • Annual contract
  • Most flexibility
  • Provides options for smaller Maintenance projects
  • Rapidly changing construction program

slide notes:

None




slide 20: Questions and Discussion

Contact Information

Ralph Adair
RTMC Integration and Systems Engineer
Ralph.adair@state.mn.us
651-234-7027


Jon Jackels
ITS Development Engineer
Jon.jackels@state.mn.us
651-234-7377

slide notes:

None

Return to List of Presentations
Office of Operations