Work Zone Mobility and Safety Program

Economic Analysis of Council Bluffs and Keg Creek ABC Projects

slide 1: Economic Analysis of Council Bluffs and Keg Creek ABC Projects

Suri Sadasivam

slide notes:

None




slide 2: Economic Analysis

What is the economic efficiency of accelerated bridge and roadway construction ?

How does accelerated construction compare with traditional option in terms of economic value?

slide notes:

None




slide 3: The Concept...

Compare Costs vs Benefits for Traditional and Accelerated Construction Options

Photo of a triangular rock balancing a flat rock horizontally on the point of the triange. Two round rocks are positioned on either side of the flat rock, in balance. One rock represents agency benefits, the other represents public benefits, indicating that agencies must balance these two interests so neither outweighs the other.

slide notes:

None




slide 4: The Steps...

Brief diagram depicting the cost elements of traditional construction, in which agency cost plus user cost equals project cost.Brief diagram depicting the cost elements of accelerated construction, in which agency cost plus user cost equals project cost.

slide notes:

None




slide 5: The Inputs...

Agency Costs Road User Costs
  • Preliminary Design and Engineering
  • Construction Costs
    • Equipment
    • Material
    • Construction labor
    • Mobilization
    • Incentives/disincentives
  • Construction Engineering
  • Traffic control
  • Law Enforcement
  • Delay costs
  • Vehicle operating costs
  • Crash costs
  • Emission costs

Plus project duration

slide notes:

None




slide 6: Compare the Alternatives

When weighing traditional construction costs against accelerated construction costs, total project cost for traditional construction is less than the total project cost for accelerated construction.

slide notes:

None




slide 7: Improvements to the 24th Street – I-29/80 Interchange in Council Bluffs, Iowa

Economic Analysis

slide notes:

None




slide 8: 24th Street – I-29/80 Interchange (Council Bluffs, IA)

KEY INNOVATION

  • Use of full-depth, precast bridge deck panels made with self-consolidating, high- performance concrete
  • Estimated construction duration
    • Cast in-place → 426 days (two seasons)
    • Precast → 175 days (less than one season)

Google map overlaid with a satellite map of the project area.

slide notes:

None




slide 9: 24th Street – I-29/80 Interchange (Council Bluffs, IA) Agency Costs


Category Cast in place Precast % Increase
Preliminary design and engineering $304,380 $516,032 70%
Bridge construction $5,073,000 $6,450,398 27%
Roadway improvements $4,807,721 $4,807,721 -
Traffic control $272,521 $272,521 -
Construction inspection $50,730 $70,954 40%
Miscellaneous $620,512 $388,636 -37%
Total $11,128,864 $12,506,262 12.4%

Increase in agency cost with precast option was $ 1.4 Million

slide notes:

None




slide 10: 24th Street–I-29/80 Interchange (Council Bluffs, IA) Road User Costs –Delay Costs

Total delay time due to work zone = 607 vehicle-hours / day

Iowa DOT estimates = $8/hr for cars and $ 24/hr for trucks

Daily RUC due to work zone = $ 6,215.68

Category Cast in Place Precast
Delay time due to work zone No difference No difference
Number of Construction Days 426
(2 seasons)
175
(< 1 season)
Total Delay Costs $2,647,880 $1,087,744

slide notes:

None




slide 11: 24th Street – I-29/80 Interchange (Council Bluffs, IA) Road User Costs – Data for Safety Costs


Google satellite map of the 24th Street-I-29/80 Interchange.


Million Veh. Miles Cast in Place Precast
I-29/80 5.96 2.45
24th street 37.64 15.46
Traffic Over Construction Period 43.60M 17.91M


Crash Rate per 1000 vehicles

Personal injury: 69

Non personal injury: 146


slide notes:

None




slide 12: 24th Street – I-29/80 Interchange (Council Bluffs, IA) Road User Costs – Safety Costs

Category Cast in place Precast
I-29/80 24th Street I-29/80 24th Street
Injury-causing crash $494,883 $59,143 $203,265 $24,312
Non-injury crash $283,005 $41,795 $116,240 $17,181
Total $878,826 $360,998

slide notes:

None




slide 13: 24th Street – I-29/80 Interchange (Council Bluffs, IA) Road User Costs

Category Cast in Place Precast
Delay Costs $2,647,880 $1,087,744
Vehicle Operating Cost No difference No difference
Crash Cost $878,826 $360,998
Total RUC $3,526,706 $1,448,742


RUC savings with precast option were about
$2 million


slide notes:

None




slide 14: 24th Street – I-29/80 Interchange (Council Bluffs, IA) Total Cost Comparison

Bar graph shows the total cost comparison for cast in place versus precast broken out by agency costs and RUC. For cast in place, the cost is $14.65 million, and for precast the cost is $13.96 million.

With Precast option

Increase in agency costs = $1.38 M
Savings in RUC = $ 2.08 M
Net savings = $ 700,000

slide notes:

None




slide 15: Reconstruction of US 6 bridge over Keg Creek, Iowa

Economic Analysis

slide notes:

None




slide 16: Reconstruction of US 6 Bridge over Keg Creek

KEY INNOVATION

  • Use of Prefabricated substructure and modular superstructure elements
  • Estimated construction duration
    • Cast in-place → 183 days (6 months)
    • Precast → 14 days

Map of the project area with the detour route and location of the bridge closure identified.

slide notes:

None




slide 17: Reconstruction of US 6 Bridge over Keg Creek – Agency Costs

Item Baseline Case As-Built Case
Bridge $1,147,178 $2,294,472
Road Improvements $305,967 $305,967
Traffic Control $3,200 $3,200
Concrete Flume $55,185 $55,185
Total Project $1,511,530 $2,658,823

Increase in agency costs with precast option was $1.15 Million

slide notes:

Traffic control includes the detour signage which is assumed to be the same for the as-built and baseline scenarios.




slide 18: Reconstruction of US 6 Bridge over Keg Creek – Road User Costs – Vehicle Operating Cost

Trucks only (9% of AADT) ~ 350 trucks

21 mile detour

Mileage costs for trucks = $ 0.81 /mile

Daily RUC due to work zone = $ 5,955.20

Category Cast in Place Precast
Detour Length No difference No difference
Number of Construction Days 183 14
Total VOC $1,089,802 $83,373

slide notes:

The VOC can be estimated conservatively by considering only commercial vehicles (light and heavy trucks) traveling the designated route due to weight restrictions on other county roads in the area.

Passenger vehicles are discounted from the VOC calculation because there are numerous county roads which could serve as non-planned detour routes preventing an accurate traffic estimation based solely on the AADT on US 6.




slide 19: Reconstruction of US 6 Bridge over Keg Creek – Road User Costs – Delay Costs

21 mile detour for trucks only (9% of AADT)

Additional travel time due to detour = 24.67 min /truck

Value of delay time = $ 25.67/hr for trucks

Daily RUC due to work zone = $ 3,684.70

Category Cast in Place Precast
Delay time due to work zone No difference No difference
Number of Construction Days 183 14
Total Delay Costs $674,300 $51,586

slide notes:

As with the VOC calculation, only delay costs occurred by commercial vehicles were considered since passenger vehicles could have chosen an alternate detour route.

$25.67 is based on Mallela and Sadasivam, Work Zone Road User Costs Concepts and Applications, 2011. Report No. FHWA-HOP-12-005, Federal Highway Administration.




slide 20: Reconstruction of US 6 Bridge over Keg Creek – Road User Costs

Category Cast in Place Precast
Delay Costs $674,300 $51,586
Vehicle Operating Costs $1,089,802 $83,373
Crash Cost No difference No difference
Total RUC $1,764,102 $134,959

RUC savings with precast option were about $1.63 million

slide notes:

None




slide 21: Reconstruction of US 6 Bridge over Keg Creek – Total Cost Comparison

Bar graph shows the total cost comparison for cast in place versus precast broken out by agency costs and RUC. For cast in place, the cost is $3.275 million, and for precast the cost is $2.793 million.

With Precast option

Increase in agency costs = $1.147 M
Savings in RUC = $ 1.629 M
Net savings = $ 481,850

slide notes:

None

Return to List of Presentations
Office of Operations