Active Traffic Management Feasibility and Screening Guide
Appendix B. Active Traffic Management Screening Checklist
General Information
|
State/Region/Corridor
|
|
Lead Agency/Agencies
|
|
Purpose of Screening
|
Projects for Planning Process; initial Systems Engineering;
Other
|
Reviewed By
|
|
Date
|
|
Get Started - Preparation
|
Complete
(Yes, In Progress, No
or Not Applicable)
|
Comments
|
Do ATM strategies support one or more regional goals?
|
|
|
Have relevant operational objectives been identified?
|
|
|
Has the roadway network been identified and defined?
|
|
|
Have ATM stakeholders been identified?
|
|
|
Has the stakeholder collaboration process been initiated?
|
|
|
Has the necessary data and other information been collected?
|
|
|
Has recent literature on ATM been identified and reviewed?
|
|
|
Additional Comments
|
|
Assess Agencies Policies and Capabilities for ATM
|
Complete
(Yes, In Progress, No
or Not Applicable)
|
Comments
|
Have ATM strategies been identified in terms of type of network?
|
|
|
Have ATM strategies been identified in terms of agency polices (both formal and informal)?
|
|
|
Have potential legal constraints and issues been identified?
|
|
|
Is supporting institutional framework in place (or will be)?
|
|
|
Additional Comments
|
|
Identify Major Roadway Segments for Potential ATM
|
Complete
(Yes, In Progress, No
or Not Applicable)
|
Comments
|
Have "major" segments been identified?
|
|
|
Do selected segments have existing TSM&O and ITS deployed?
|
|
|
Will segments likely benefit from ATM; and for what reasons:
|
|
|
|
|
|
|
|
|
|
|
|
|
Have other TSM&O strategies been considered?
|
|
|
Additional Comments
|
|
Analyze and Prioritize Individual Roadway Links & ATM Strategies
|
Complete
(Yes, In Progress, No
or Not Applicable)
|
Comments
|
Have individual links within major segments been identified?
|
|
|
Have links been analyzed and prioritized for ATM deployment?
|
|
|
Have appropriate ATM strategies been identified for each link:
|
- Dynamic speed limits/lane assignment
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- Adaptive Traffic Signal Control
|
|
|
|
|
|
|
|
|
|
|
|
Have identified ATM strategies for each link been combined?
|
|
|
Have any gaps in ATM coverage been addressed for continuity?
|
|
|
Additional Comments
|
|
Estimate Benefits and Costs and Finalize ATM Recommendations
|
Complete
(Yes, In Progress, No
or Not Applicable)
|
Comments
|
Have all costing assumptions been made?
|
|
|
Have relevant measures of effectiveness (for calculating benefits) been identified?
|
|
|
Have ATM benefits (monetized) and costs been estimated and compared (B/C ratio)?
|
|
|
Have priorities (by links and strategies) been finalized and presented to decision makers?
|
|
|