Houston Managed Lanes Case Study: The Evolution of the Houston HOV System


CHAPTER FOUR—DEVELOPING AND OPERATING MANAGED LANES

This report summarizes the development, operation, and use of the HOV system in Houston and the development of managed lanes in one corridor. The institutional arrangements and the factors influencing the development of the system were also described. This chapter summarizes some of the issues that may need to be examined when managed lanes are being considered in an area, as well as those typically associated with operating projects. It also highlights current and future FHWA activities related to advancing the state-of-the-practice associated with the use of managed lanes.

Issues to be Considered

A number of issues may need to be examined when HOV and managed lanes are being considered in an area or when changes to an existing facility are being contemplated. While many of these issues are similar to those associated with HOV facilities or other transportation improvements, some are unique to the special characteristics of managed lanes. This section summarizes some of the issues that may arise with managed lanes, as well as those associated with ongoing management and operation.

Federal Interest in HOV Operational Changes

FHWA has periodically issued guidance on HOV facilities. The most recent Program Guidance on HOV Operations was issued on March 28, 2001 (36). The Program Guidance identifies the circumstances under which federal action is required to initiate changes in the operation of an HOV facility, and the federal review process and requirements to be used in these situations. The Program Guidance is available on the FHWA Internet site at https://www.fhwa.dot.gov/legsregs/directives/policy/index.htm.

Federal action is required when significant changes are proposed to existing HOV facilities constructed with federal funds. Significant changes include major alterations in operating hours and converting an HOV lane to general-purpose use. Minor modifications in operating hours and changing from different multi-person occupancy levels (from 3+ to 2+, for example) do not require federal approval. Coordination and consultation with FHWA is appropriate even when an operational change is only being considered or discussed, however, as a basis to determine what may be needed for actual changes to occur.

The Program Guidance identifies the information to be included as part of a federal review. Examples of needed information include original studies and plans for the HOV facility, project agreements, commitments made in the environmental process, operational assessments, analysis of future conditions, examination of alternative operating scenarios, and possible impacts on air quality levels and plans. The Program Guidance further outlines the federal review requirements related to air quality conformity, the state implementation plan, the congestion management system, the National Environmental Policy Act (NEPA) process, and other issues.

The Program Guidance and other available documents support the need to examine HOV systems on a regional, not just individual project, basis. Elements in this approach include a multi-year regional HOV system strategic plan, which is integrated into the metropolitan area long-range plan, and a multi-agency program to manage implementation of the system plan and to support day-to-day operation of HOV facilities and supporting services. This approach allows for the long-term regional commitment for infrastructure improvements, the careful phasing of operating segments, and coordinating the development and operation of supporting services, facilities, and policies.

Current and Future Activities

FHWA and other groups have begun a variety of activities related to managed lanes. Additional activities are planned to help share information related to managed lanes and to help advance the state-of-the-practice. This section highlights a few examples of FHWA-sponsored activities.


Back to Top

Previous | Table of Contents | Next