Transportation Management Plan
I-5/I-805 Widening Project
Transportation Management Plan I-5/I-805 Widening Project - Final Rule on Work Zone Safety and Mobility - FHWA Work Zone
FHWA Work Zone
Printable Version [PPT, 2.7MB]
To view PPT files, you need the Microsoft
PowerPoint Viewer.
Contact Information: WorkZoneFeedback@dot.gov
Slide 1. Caltrans Transportation Management Plan
I-5/I-805 Widening Project
California Department of Transportation
Traffic Operations
District Traffic Manager Branch
District 11, San Diego
January, 2002
Slide 2. TMP Objectives
- To provide a working window in which the Contractor can complete meaningful work.
- To reduce congestion and improve safety at the I-5/I-805 Merge.
- To maintain freeway access for local communities.
- Increase capacity and provide for future improvements along I-5 corridor.
Slide 3. TMP Strategies Overview
- Public Information
- Motorist Information
- Incident Management
- Construction Strategies
- Demand Management
- Alternative Route Strategies
Slide 4. Table 1 – Public Information
Public Information | Location | Responsible Party | Implementation Cost | Comments |
---|---|---|---|---|
Mailing List Database | Various | Public Affairs | $500.00 | Resident Engineer to assist |
Open House | (To be decided) Local School | Public Affairs | $5,000.00 | Resident Engineer to assist |
Construction Bulletin/Ad Distribution | Available @ Const. Field Office | Public Affairs | None | Resident Engineer to assist |
Construction Bulletin/Ad Distribution | Mailed | Public Affairs | $32,000.00 | |
Construction Bulletin/Ad Distribution | Hand Delivered | Public Affairs | $10,000.00 | |
News Releases | Not applicable | Public Affairs | No direct cost/Support only | 3 News releases/month throughout the length of the project |
Radio Ads | Not applicable | Public Affairs | $403,000.00 | Resident Engineer to provide updated project information |
Advertise Park & Ride Lots | Public Information Officer to decide | Public Affairs | $10,000.00 | Not applicable |
Print Advertisement | Various Newspapers | Public Affairs | $147,000.00 | Resident Engineer to provide updated project information |
Sub Total: | $607,500.00 | Use $608,000.00 |
Slide 5. Table 2 – Motorist Information
Motorist Information | Location | Cost of Implementation | Construction Time Prior to 5/805 Project Begin Date | Approve | Reject |
---|---|---|---|---|---|
Fixed Changeable Message Signs (FCMS) | As shown on page 18 | 3 @ $250,000 each | 2 years to design and construct duration | ||
Portable Changeable Message Signs (PCMS) | Per Detour Plans/R.E. | 8 @ $10,000 each | Not applicable | ||
Ground Mounted Signs | Per Stage Construction Plan | $5,000 | Not applicable | ||
Highway Advisory Radio | To be decided | Not applicable | Not applicable | ||
Caltrans Highway Information Network (CHIN) | Not applicable | Not applicable | Information updated daily | ||
Sub Total: | $835,000.00 |
Slide 6. Motorists Information
- Use (3) fixed Changeable Message Signs (CMS) at the following locations.
- On northbound Route 5. 1–2 miles south of the off-ramp to eastbound SR-52.
- On southbound Route 5. 1–2 miles north of the off-ramp to eastbound SR-78.
- On northbound Route 805. 1–2 miles south of the off-ramp to eastbound SR-52.
- Use (8) Portable Changeable Message Signs (PCMS) (part of the contract).
Slide 7. Existing CMS Map
Slide 8. CMS Locations
Sign Loc. | CMS No. | Dir. | Rte. | Post Mile | General Location |
---|---|---|---|---|---|
1 | CMS 1 | NB | 15 | 10.627 | SO Rte. 52 interchange (R/S) |
2 | CMS 2 | NB | 15 | 10.874 | JSO Rte. 52 interchange (R/S) |
3 | CMS 3 | NB | 15 | 11.252 | JNO Rte. 52 interchange (C/D) |
4 | CMS 4 | NB | 15 | 11.508 | NO Rte. 52 interchange (C/D) |
5 | CMS 5 | NB | 163 | 10.070 | JNO Rte. 52 interchange (R/S) |
6 | CMS 6 | NB | 163 | 10.260 | NO Rte. 52 interchange (R/S) |
7 | CMS 7 | NB | 163 | 10.610 | JSO Kearny Villa Road (R/S) |
8 | CMS 8 | NB | 163 | 11.130 | NO Kearny Villa Road (R/S) |
9 | CMS 9 | SB | 15 | 19.101 | SO Ted Williams Pkwy (R/S) |
10 | CMS 10 | SB | 15 | 19.319 | Ted Williams Pkwy O/C |
11 | CMS 11 | SB | 15 | 19.903 | SO Carmel Mountain Road (R/S) |
12 | CMS 12 | SB | 15 | 21.134 | Camino del Norte (R/S) |
13 | 1 | SB | 163 | 9.009 | SB 163 N/O Claremont Mesa Blvd |
14 | 2 | NB | 163 | 5.458 | NB 163 N/O Friars Rd |
15 | 3 | NB | 805 | 18.296 | NB 805 N/O I-8 |
16 | 4 | SB | 805 | 22.791 | SB 805 N/O Clairemont Mesa Blvd |
17 | 5 | WB | 8 | 14.345 | WB 8 W/O Main Street |
18 | 6 | NB | 5 | 14.753 | NB 5 @ J Street |
19 | 7 | SB | 15 | 13.569 | SB 15 @ Miramar Way |
20 | 8 | SB | 5 | SB I-5/SB 805 split | |
21 | 9 | WB | 54 | 3.527 | WB 54 W/O Woodman Ave |
22 | 10 | NB | 5 | 6.660 | NB 5 @ L Street (Chula Vista) |
23 | 11 | NB | 805 | 6.520 | N/B 805 @ E/H Street |
24 | 12 | EB | 52 | 2.361 | EB 52 @ Genesee Ave. |
25 | 13 | WB | 52 | 8.995 | WB 52 @ Santo Road |
26 | 14 | NB | 805 | 12.236 | NB 805 @ Imperial Ave |
27 | 15 | NB | 15 | 2.680 | NB 15 N/O Rte. 94 interchange |
28 | 16 | SB | 805 | 16.701 | SB 805 N/O El Cajon Blvd |
29 | 17 | NB | 5 | 16.700 | South of W. 18th Street |
30 | 18 | NB | 5 | 29.600 | North of Washington St |
31 | 19 | NB | 5 | 79.100 | South of Tamarack Ave |
32 | 20 | EB | 8 | R1.3 | West of Taylor St |
33 | 21 | WB | 8 | KP2.7 | East of Taylor St |
34 | 22 | WB | 8 | KP11.5 | East of Waring Rd |
35 | 23 | WB | 94 | KP9.3 | East of Kelton Rd |
36 | Coro. 1 | EB | 75 | JWO Toll Plaza (west parking lot) | |
37 | Coro. 2 | SB | 5 | 14.525 | JSO "J" Street O/C |
38 | Coro. 3 | NB | 5 | 13,652 | JNO 28th Street near Coronado OR |
39 | Coro. 4 | USN | 282 | 0.720 | Alameda Street USNAS Main Gate |
40 | Coro. 5 | USN | 75 | 17.800 | Rendova Road USN Gate #1 |
41 | Coro. 6 | USN | 75 | 17.600 | Guadalcanal St. USN Gate #3 |
42 | Coro. 7 | WB | 75 | 20.497 | JEO Toll Plaza (foot of the bridge) |
43 | Bor. 1 | SB | 805 | 4.417 | Orange Avenue O/C |
44 | Bor. 2 | SB | 5 | 4.317 | JSO Coronado Ave. (NO Hollister) |
45 | Bor. 3 | NB | 805 | 0.298 | Camino de la Plaza O/C (right sign) |
46 | Bor. 4 | NB | 5 | 0.292 | Camino de la Plaza O/C (left sign) |
47 | Dscnso | EB | 8 | R33.500 | JWO E. Willow (R/S) |
48 | Imperial | WB | 8 | R13.300 | At SR 98 (Ocotillo) Imperial County |
Slide 9. Table 3 – Incident Management
Incident Management | Total Cost | Comments |
---|---|---|
Construction Zone Enhanced Enforcement Program (COZEEP)
|
$1,700,000.00 | Resident Engineer to decide when to use COZEEP |
Freeway Service Patrol (FSP)
|
$867,000.00 | New contract requires 3–4 months advance planning |
Traffic Management Team (TMT)
|
EA charged | Resident Engineer to coordinate with TMT |
Web Camera
|
$200,000.00 | Live connection to web site for public access |
Sub Total: | $2,767,000.00 |
Slide 10. Freeway Service Patrol Map
Slide 11. The Following New FSP Hours Are Recommended
- 5:30 AM to 11:30 AM on Weekdays
Additional two AM hours are recommended - 2:00 PM to 8:00 PM on Weekdays
Additional two PM hours are recommended - 2:00 PM to 6:00 PM on Saturday
Additional of four hours are recommended - 2:00 PM to 6:00 PM on Sunday
Additional of four hours are recommended
Slide 12. Table 4 – Construction Strategies
Construction Strategies | Comments |
---|---|
Lane Closure Charts
|
Resident Engineer to work with District Traffic Manager Branch and apply DD 60 |
Incentive & Disincentive Clause
|
Resident Engineer to work with District Traffic Manager Branch and apply DD 60 |
Total Facility Closure
|
Resident Engineer to work with District Traffic Manager Branch and apply DD 60 |
Late Lane Closure Opening
|
Resident Engineer to work with District Traffic Manager Branch and apply DD 60 |
Slide 13. Table 5 – Demand Management
Location | # of Parking Spaces Available/or Potential of Expanding | Existing Public Affairs Involvement | New Public Affairs Involvement | Construction Cost | Shuttle Cost per Year | Approve | Reject |
---|---|---|---|---|---|---|---|
Lot #5 Oceanside 1667 Maxson St. | 74 | Yes | Not applicable | $52,800.00 | |||
Oceanside on N. Coast Hwy | 70 | Yes | $30,000.00 | Included with Lot #5 | |||
Lot #32 at La Costa Avenue | 58 | Yes | Not applicable | $52,800.00 | |||
Lot #62 & #47 at Calle Magdelena | 27 + 36 | Yes | Not applicable | $52,800.00 | |||
On Encinitas Boulevard | 55 | Yes | $29,500.00 | $52,800.00 | |||
On Turf Rd. next to the Del Mar Fairgrounds | 35 | Yes | $21,000.00 | $52,800.00 | |||
Under SR 56, East of I-5, south of Carmel Valley Rd. | 100 | Yes | $45,000.00 | Not applicable |
Location | Condition | Construction Cost | Shuttle Cost per Year | Approve | Reject |
---|---|---|---|---|---|
Ramp Metering (Temp) | Adjusting timing on Westbound SR-56 connector to Southbound I-5 | Not applicable | Not applicable | ||
HOV Lanes/Ramps (New or Convert) | Restripe existing #1 lane at 5/56 to SB 5 into an HOV lane | $10,000.00 | Not applicable | ||
**Ride Share Incentives | Free local shuttle between coaster station & Park & Ride Lots | $135,500.00 | $264,000.00 |
**To be applied only when SR-56 is completed and open to public traffic (1 year).
Total construction cost including the Ride and Share incentives cost = $400,000.00.
Slide 14. Park & Ride Location Map
Slide 15. Coaster Photo
Slide 16. Alternative Route Strategies
- Stripe and open to vehicles Northbound bypass connector "Northbound bypass Lane" thus allowing utilization of #5 lane up to Del Mar Heights Rd.
- Accelerate construction of Vista Sorrento Parkway via coordination between developer and City of San Diego anticipated completion (Fall of 2002).
- Ferry Service: A high-speed ferry service between Oceanside and down town San Diego (details being finalized).
- Increase Ridership in the Coaster.
Slide 17. All Park & Ride Are at Full Capacity
Station | Capacity | 9/4/2001 | 9/6/2001 | 9/11/2001 | 9/13/2001 | 9/18/2001 | 9/20/2001 | 9/25/2001 | 9/27/2001 |
---|---|---|---|---|---|---|---|---|---|
Oceanside | 633 | 633 | 633 | 498 | 633 | 633 | 633 | 633 | 633 |
Carlsbad | 298 | 295 | 300 | 209 | 296 | 295 | 292 | 293 | 290 |
Poinsettia | 335 | 296 | 333 | 226 | 322 | 318 | 316 | 332 | 318 |
Encinitas | 236 | 218 | 231 | 149 | 230 | 229 | 230 | 232 | 227 |
Solona Beach | 332 | 283 | 253 | 210 | 226 | 194 | 242 | 237 | 229 |
Total | 1,834 | 1,725 | 1,750 | 1,292 | 1,707 | 1,669 | 1,713 | 1,727 | 1,697 |
At Carlsbad Coaster 100 parking spaces to be added by January 1st, 2002, by NCTD.
Encinitas: Adding 75–100 spaces and would be available by March 2002 – NCTD.
Slide 18. Summary of TMP Elements
Elements | Costs |
---|---|
1. Public Information | $608,000.00 |
2. Motorist Information | $835,000.00 |
3. Incident Management | $2,767,000.00 |
4. Construction Strategies | $0.00 |
5. Demand Management | $400,000.00 |
6. Alternative Route Strategies | $10,000.00 |
Total Cost: | $4,620,000.00 |
Slide 19. TMP Elements and Costs
Slide 20. Total Costs*
- Total TMP Budget = approx. $4.6 M
- Total Project Budget = approx $170 M
- TMP Costs = 2.7% of Total Project Costs
*Note: This slide was not part of the original Caltrans presentation. It is based on information received from the Senior Resident Engineer in June 2006.