Description of Slide 31. Implementation: Timeline
Description
This timeline shows the estimated time requirements for successive actions in the implementation process. The process lasts from the beginning of 2005 until October 12, 2007.
- January 2005 to September 2005: FHWA implementation guidance documents developed
- September 2005 to February 2006: Update and/or develop work zone safety and mobility policy
- February 2006 to August 2006: Update and/or develop angency-level processes and procedures
- April 2006 to October 2006: Update and/or develop project-level procedures
- October 2006 to January 2007: Identify candidate project(s) for early implementation
- January 2007 to July 2007: Implement provisions on early implementation project(s)
- March 2007 to August 2007: Develop lessons learned from early implementation(s) (Modify policies, processes, and procedures appropriately)
- July 2006 to October 12, 2007: Implement provisions on all projects (with allowance for variances)