2009 Process Review Louisiana's Work Zone Program
slide 1: 2009 Process Review Louisiana's Work Zone Program
Betsey Tramonte
Safety Specialist
FHWA – LA Division
Barry Lacy
Work Zone Engineer, P.E.
LA Department of Transportation and Development (DOTD)
Download the Printable Version [PDF,
299 KB]
You will need the Adobe Acrobat Reader to view this PDF.
slide 2: Purpose/Objective
- Document compliance with 23CFR630 Subpart J and Subpart K and the MUTCD
- Review of DOTD policies regarding temporary traffic control
- Review of procedures at the project level to gage compliance with DOTD policies
slide 3: Scope
- Conduct FHWA Work Zone Self Assessment to review work zone program area
- Conduct site visits of 18 ongoing work zones in each of DOTD's nine districts
- Document findings
- Provide report to stakeholders
slide 4: Team Members
- FHWA Louisiana
- LA DOTD Construction Section
- Louisiana's Work Zone Task Force
slide 5: Findings/Recommendations
slide 6: Finding 1 – Project Planning and Programming
- In the FHWA Work Zone Self-Assessment, LA scored lower in 2009 than previous years
slide 7: Recommendation 1 – Project Planning and Programming
- Incorporate checklist for work zone traffic control impacts in Stage Zero
- DOTD's Planning and Programming Section attend Work Zone Task Force meetings
slide 8: Finding 2 – Transportation Management Plan (TMP)
- DOTD does not have an official policy requiring a TMP for all federal-aid projects.
slide 9: Recommendation 2 – Transportation Management Plan
- DOTD revise existing Lane Closure EDSM to require a TMP on all significant projects
slide 10: Finding 3 – Night Inspections of Traffic Control Devices
- According to DOTD policy, traffic control devices shall be inspected by the Traffic Control Supervisor once a week during nighttime periods.
- Only documented on 50% of projects
slide 11: Recommendation 3 – Night Inspections of Traffic Control Devices
- DOTD project engineers enforce contractor inspection of traffic control at night
slide 12: Finding 4 – Media Releases
- According to DOTD policy, contractor shall contact media on a weekly basis or more often as needed
- Currently, DOTD handles all contact with the media on an as needed basis
slide 13: Recommendation 4 – Media Releases
- DOTD should relieve the contractor from responsibility of media contact unless a project's significance determines the need
slide 14: Finding 5 – Lighting Plan
- According to DOTD policy, an approved lighting plan shall be on file for all nighttime construction projects
- 3/5 projects reviewed with nighttime work DID NOT have a plan
slide 15: Recommendation 5 – Lighting Plan
- DOTD project engineers should check all projects with nighttime work for a lighting plan
- Lighting plan should be checked nightly for compliance
slide 16: Finding 6 – WZ Deficiencies
- Conflicting signs properly treated
- Variable Message Signs
- Channelizing devices
- Truck Mounted Attenuators
slide 17: Recommendation 6 – WZ Deficiencies
DOTD and FHWA note trends and look for deficiencies in field review
- Conflicting signs properly treated
- Variable Message Signs
- Channelizing devices
- Truck Mounted Attenuators
slide 18: Observations/Recommendations
slide 19: Observation 1: Temporary Traffic Control Plan
- 66% of projects reviewed had TTC plans
- 1/4 of these projects, TCS didn't have current copy of plans revisions
- 33% of projects reviewed had standardized traffic control plan as TTC plan
slide 20: Recommendation 1: Temporary Traffic Control Plan
- Temporary Traffic Control plans should be designed specific to the construction project since each work zone is unique
- All revisions to traffic control plans should be submitted by the contractor to the project engineer
slide 21: Observation 2: Work Zone Safety Training
- Coordinated, collaborative training is not conducted for all stakeholders
- DOTD work zone training exists but is stovepiped for stakeholders creating miscommunication
- Law Enforcement example
slide 22: Recommendation 2: Work Zone Safety Training
- Conduct collaborative training for all personnel with a role in work zone safety at the project level
- All District Construction Field Personnel
- DOTD Area Engineers, Project Engineers, Design Engineers, Traffic Engineers, Private Contractors, Law Enforcement
slide 23: DOTD Response
- Transportation Management Plan Training
- DOTD led audits of lighting plan on projects
- Site Manager Diaries to manage deficiencies
- Ability to suspend contractor's operation for failure to address deficiencies
- Current temporary traffic control plans
- Louisiana Specific Work Zone Training Course
slide 24: What worked and didn't work...
- That could have worked better...
- Start early
- Be clear on scope
- Focus on fewer things in greater detail
- That worked!
- Collaboration among partners
- Management support of review from both state and federal perspective
slide 25: QUESTIONS?
slide 26: Thank You!