Best Practice
BEST PRACTICE:
F3−2: Narrow Window for On−Site Construction
DESCRIPTION:
On selected projects, the Oregon Department of Transportation specifies a restricted time frame for on−site construction within the allowable contract time. For example, on−site work on an overlay project might be limited to 30 consecutive calendar days although the contractor may have 100 calendar days to complete the entire project.
REASON(S) FOR ADOPTING:
This practice was adopted to minimize the length of time traffic is disrupted and to present a more positive image to the public.
PRIMARY BENEFIT(S):
Projects are completed in a more timely manner with minimal disruption.
MOST APPLICABLE LOCATION(S)/PROJECT(S):
This policy is most applicable to overlay projects on 2−lane rural highways, but can be applied to other work.
STATE(S) WHERE USED:
Oregon
SOURCE/CONTACT(S):
Nick Fortney, Transportation Safety Engineer, FHWA Oregon Division Office
Phone: (503) 587−4721
E−mail: nick.fortey@fhwa.dot.gov