Best Practice
BEST PRACTICE:
G4−13: Water Filled Barrier in Work Zones
DESCRIPTION:
The North Carolina Department of Transportation (NCDOT) has used water filled barrier as a substiture for temporary precast concrete barrier on projects to protect travelers from construction areas as well as drop−off conditions and additional protection for the construction workers. NCDOT typically uses water filled barriers on projects with traffic speeds less than 45 mph; however occasionally water filled barriers are used in work zones with traffic speeds up to 60 mph.
REASON(S) FOR ADOPTING:
To protect travelers and workers while more easily enabling access to homes and businesses.
PRIMARY BENEFIT(S):
Increased safety for travelers and construction workers.
MOST APPLICABLE LOCATION(S)/PROJECT(S):
Urban and suburban work zones. These are effective in areas where the barrier has to be opened to allow access to homes and businesses.
STATE(S) WHERE USED:
North Carolina
SOURCE/CONTACT(S):
Steve Kite, North Carolina DOT
Phone: (919) 662−4339
E−mail: skite@ncdot.gov