Work Zone Mobility and Safety Program

Feasibility Study on Implementation of CA4PRS in Oklahoma

slide 1

September 23, 2010


Saeed Abdollahipour, doctoral student
David Jeong, Ph.D. Assistant Professor

School of Civil & Environmental Engineering Oklahoma State University

View the PDF Version [1.1 MB]
Download the free Adobe Reader to view PDFs You will need the Adobe Reader to view the PDFs on this page.




slide 2

Outline

  • Introduction
  • CA4PRS Workshop
  • Case Studies
  • Resource Profile Information
  • Development of a Model for Resource Profile Information
  • Limited Number of Activities
  • Conclusions



slide 3

Introduction






slide 4

Roads Condition in Oklahoma

  • 40% of Oklahoma's major roads are rated in poor or mediocre condition (ASCE 2009).
  • Costs Oklahoma motorists $1 billion a year in extra vehicle repairs and operating costs (OTC 2009).
  • Total projected revenues from FY2009 to FY2028 amount to 39 percent of needs, resulting in a shortfall of $16.9 billion (ODOT 2009).
  • Urgent need to improve management strategies; minimize the costs and optimize rehabilitation activities.



slide 5

Objectives

  • Study the feasibility of using CA4PRS for PCC pavement rehabilitation projects in Oklahoma



slide 6

CA4PRS Workshop






slide 7

CA4PRS One day Workshop

  • Date: April 13, 2010
  • Instructor: Dr. E.B. Lee
  • Participants: ODOT Engineers
  • Survey Topics:
  • General knowledge of the program
  • Applicability to ODOT operations
  • Potential for improvement of process
  • Availability of information
  • Usability of the program



slide 8

CA4PRS One day Workshop

  • Questionnaire

Snapshot of a questionnaire used in the one-day CA4PRS workshop.


slide 9

Survey Results


Graph shows the ODOT pre-demonstration survey results compared with the post-demonstration survey results. While all questions scored a mean of less than 3.5 (neutral) pre-demonstration, only two questions continued to rate a mean score below 3.5 (neutral) post-demonstration.


slide 10

Interpretation of Results

  • A general increase (approximately 20%) in the level of agreement with the potential applicability of the program for analysis of procedures used in Oklahoma.
  • A general increase in the level of agreement of participants with the idea that CA4PRS could improve ODOT current practices.
  • Participants have been consistent with their perception that ODOT does not have the readily available input information to run CA4PRS (Q13, Q15).



slide 11

Case Studies






slide 12

Case Projects

  • Two PCC pavement rehabilitation projects studied (I-35 & I-40)
  • I-35 is finished / I-40 is ongoing

Map of the state of Oklahoma's roadway system. Project locations on Interstates 35 and 40 are labeled.


slide 13

I-35 Scheduling & Traffic Analysis






slide 14

Project Overview

  • North-South Interstate highway
  • Two lanes in each direction
  • Project starts from the mile post of 197 and ends in the mile post of 204

Map highlighting the 5.57 mile stretch of the I-35 project area.


slide 15

Rehabilitation Profile


Diagram represents two cutaways, one of the existing pavement and the rehabilitated pavement for the I-35 project.


slide 16

Contractual Features

  • A+B Contract; A=$13.1 M & B=275 c-days
  • Incentive/Disincentive → $7,500/c-day
  • Incentive Cap → 90 c-days
  • Started on August 2009
  • Finished on May 2010
  • Actual Duration → 275 c-days



slide 17

Problems Faced During Analysis

  • The project had to be divided into different phases in order to be modeled by CA4PRS.
  • Resource profile information had to be collected by performing regular site visits.
  • Neither ODOT nor contractors had information regarding Mobilization, Demobilization, and lead lag times.



slide 18

Phasing plans

  • Phase 1: 6' concrete temporary shoulder
  • Phase 2: Construct X-overs
  • Phase 3: 2x12'+1x14' Overlay & Full Depth
  • Phase 4: 2x12'+1x14' Overlay & Full Depth
  • Phase 5: Open lanes
  • Phase 6: 2x12' inside lanes mill & overlay
  • Phase 7: 2x12' outside lanes mill & overlay

A series of images represent the 7 phases described above.




slide 19

Analysis & Results

Phase Description Duration (working days) User cost ($)
1 NB temporary shoulder 15 51,108
2 Pave crossovers 5 14,720
3&4, Section 1 SB & NB Concrete overlays 47 176,736
3&4, Section 2 SB & NB full depth reconstruction 85 498,027
6&7 Mill and overlay 4 23,552
8 Other activities 38 322,869
Total  194 1,087,012

  • Considering 15% expansion; the final suggested duration for this project would be 230 working days or 316 c-days.
  • Has been scheduled and finished by the contractor in 200 working days or 275 c-days.
  • Actual productivity rate of the project was higher than CA4PRS calculations.
  • User cost per c-day = $4,000 < Actual Incentive = $7,500 / c-day



slide 20

I-40 Scheduling & Traffic Analysis






slide 21

Project Overview

  • West-East Interstate highway
  • Two lanes in each direction
  • Project starts from the mile marker 125 to mile marker 136.
  • Still on going

Map highlighting the 7.31 mile stretch of the I-40 project area.


slide 22

Contractual Features

  • A+B Contract; A=$59 M & B=800 c-days
  • Incentive/Disincentive → $15,000/c-day
  • Incentive Cap → 150 c-days
  • Liquidated damage →$2,000/c-day
  • Lane Rental Fee → $30,000/hour
Time Monday thru Friday Saturday Sunday
12 am – 6 am $0 $0 $0
6 am – 9 am $30,000 $0 $0
9 am – 12 pm $30,000 $0 $0
12 pm – 6 pm $30,000 $30,000 $30,000
6 pm – 9 pm $30,000 $30,000 $0
9 pm – 12 am $0 $0 $0



slide 23

Unique Features

  • Phase 1: 10' concrete temporary shoulder
  • Phase 2: 28' EB widening
  • Phase 3: Reconstruction and WB widening
  • Phase 4: EB Reconstruction

A series of iconic images represent the 4 phases described above.




slide 24

Problems Faced During Analysis

  • Most of the activities could not be modeled by CA4PRS.
  • The project was a combination of widening and rehabilitation which is not supported by CA4PRS.
  • Project was divided into four phases for traffic analysis.



slide 25

Results and Analysis

  Duration User Cost Queue
Phase 1 50 $528,958.00 Saturdays 6 am - 12 pm
Phase 2 200 $1,589,221.00 -
Phase 3 200 $3,178,443.00 -
Phase 4 100 $1,589,221.00 -
Total   $6,885,843.00  

  • User cost per c-day = $8,700 < Actual Incentive = $15,000 / c-day
  • Traffic demand is more than capacity from 6 am to 12 pm during Saturdays
  • User cost for closing one lane = $27,000/hr ≈ Lane Rental Fee = $30,000/hr

Two graphs that illustrate that traffic demand is more than capacity from 6 am to 12 pm on Saturdays.




slide 26

Resource Profile Information






slide 27

Scheduling Process of CA4PRS

Diagram of inputs and outputs that reflect the scheduling process of CA4PRS. Inputs include productivity rate of activities in cu. yd/hr, section profile information, productivity rate of activities in miles/hour, and effective closure duration. Output is productivity rate of closure in miles/closure.

  • The results are highly dependent on resource profile information.



slide 28

Observed Resource Information

Resource Description Suggested Input Data Minimum Observed Maximum Observed Mean CA4PRS Manual
Demolition Hauling Truck
  • Truck Capacity: 23 ton
  • Trucks per Hour per Team: 4-6
  • Efficiency: 0.45
  • Number of Teams: 1
  • Team Efficiency: 0.94
3 5 4 8 to 13
Base Delivery Truck
  • Truck Capacity: 8 cu. yd
  • Trucks per Hour: 6-8
  • Efficiency: 0.90
2 20 7 -
Batch Plant
  • Capacity: 200 cu. yd/hour
  • Number of Plants: 1
Concrete Delivery Truck
  • Truck Capacity: 9 cu. yd
  • Trucks per Hour: 14-16 Efficiency: 1.0
5 22 14 9 to 16
Paver
  • Speed: 5.5 ft/min
  • Number of Pavers: 1

(Productivity Rate Required in Oklahoma) < (Productivity Rate Required in California)




slide 29

Assessment of Resource Analysis

Output of CA4PRS Scheduling Analysis
Resource Allocated Utilized
Demolition Hauling Truck (per Hour per Team) 10 10
Base Delivery Truck (per Hour) 5 5
Batch Plant (cu-yd/hour) 120 120
Concrete Delivery Truck (per Hour) 20 16.7
Paver Speed (ft/min) 6.6 4.6



slide 30

Development of a Model for Resource Profile Information






slide 31

Cyclone Simulation Model

Diagram depicts the concrete delivery cycle, which is as follows: Travel to batch plant, load at plant, travel to job site, wait to dump, find spot available, dump concrete, return, wait load, load at plant, and return.
Tasks Duration (min) Resources Numbers
Load at Plant 5 Batch Plant 1
Travel to Job Site 15 Trucks 10
Dump 10 Spot Available 1
Return 15



slide 32

Graph depicts productivity rate and optimum number of trucks, illustrating that productivity does not increase necessarily by increasing CA4PRS input variable or by increasing the total number of trucks, that there is a maximum productivity rate which is achieved by the CA4PRS input of 12 Trucks per Hour, and that the optimum number of trucks is different from CA4PRS input.

  • Productivity does not increase necessarily by increasing CA4PRS input variable or by increasing the total number of trucks.
  • There is a maximum productivity rate which is achieved by the CA4PRS input of 12 Trucks per Hour.
  • Optimum number of trucks (which is required by contractors) is different from CA4PRS input.



slide 33

Distance from Batch-Plant

Graph depicts maximum productivity rate and optimum number of trucks, illustrating that the further the distance from the Batch Plant the less the productivity rate is and that the further the distance from the Batch Plant the more trucks are needed, but even by allocating more trucks the maximum productivity rate decreases.

  • The further the distance from the Batch Plant the less the productivity rate is.
  • The further the distance from the Batch Plant the more trucks are needed, but even by allocating more trucks the maximum productivity rate decreases.



slide 34

Limited Number of Activities






slide 35

CPM Analysis

Image shows a series of project schedules with differing end dates, including September 7, Setpember 14, and September 9. The variability in dates is due to differing sets of activities accounted for in each project schedule.

  • The relationship between the main activities in CA4PRS and other rehabilitation activities not available in CA4PRS is critical



slide 36

Conclusions






slide 37

Results

  • Contractor finished the project 30 working days sooner than CA4PRS schedule.
  • User cost calculated by CA4PRS ($4,000/day) is smaller than actual incentive amount ($7,500/day). (the incentive amount has been set higher to encourage the contractor to accelerate the project)
  • Scheduling module cannot be used properly for large size rehabilitation projects (I-40).
  • Lane rental fee calculated by CA4PRS in I-40 project is almost the same as ODOT calculations.
  • The ODOT user cost calculation process is not considering the difference between traffic patterns during weekdays and weekends. CA4PRS provide the required platform for a more comprehensive work zone traffic analysis.
  • The Agency Cost module was not utilized in case projects.



slide 38

Recommendations

  • ODOT; based on experience.
  • Innovative; compare What-If scenarios, the optimized scenario is selected.
Flow diagram that summarizes the ODOT experience and transfers it into a universal 'What If' analysis.


slide 39

Recommendations

  • The Construction Windows and Working Methods are limited in Oklahoma therefore there is a limited number of what-if scenarios.
  • Currently, there is no any reliable resource profile database in ODOT.
  • The daily traffic distribution data is required for Work-Zone traffic analysis.
    • ODOT is encouraged to start collecting resource profile information for scheduling analysis.
    • ODOT may start scheduling the projects with CA4PRS in the inception phase but they are not encouraged to use CA4PRS scheduling module extensively until the necessary data base is available.
    • ODOT is encouraged to start using the Work-Zone Analysis module of CA4PRS and replace it with the existing spreadsheet program.



slide 40

Thank You




Office of Operations