Getting More by Working Together — Opportunities for Linking Planning and Operations


2. Opportunities for Linking Planning and Operations


2.5 Funding and Resource Sharing


BACKGROUND

In developing strategies to fund M&O activities, regions have an opportunity to promote new relationships and arrangements that support broad regional systems management perspective and better link operations with regional planning. For example, a planning and programming process that places a high priority on interjurisdictional coordination can encourage normally independent practitioners to collaborate and identify opportunities for shared equipment and facilities. Funding strategies can also be used to help ensure implementation of M&O objectives developed through the planning process or to attract new operations stakeholders to planning forums. This section discusses strategies that use funding and resource sharing to improve coordination between planning and operations.

What Is Funding and Resource Sharing?

Funding and resource sharing refers to a variety of arrangements by which transportation and other operating agencies collaborate to submit funding requests, develop pooled funding mechanisms, or share equipment and facilities. As a linkage mechanism, this also refers to efforts to coordinate between visions of transportation systems management that are discussed in plans and the regional funding policies and commitments that are needed to make those visions a reality.

What Are the Sources of Funds for Management and Operations Efforts?

A number of funding sources can support management and operations activities and equipment. In practice, however, funding for system management and operations must often rely on the discretionary budgets of individual jurisdictions and/or agencies.

Federal policies allow several funding sources to be used for regional systems management and operations programs. In TEA-21, the Federal-aid Highway Program continued eligibility for Federal funding of operating costs for traffic monitoring, management, and control systems. Such operating costs can include both the establishment and continuous operation of management systems such as integrated traffic control systems, incident management programs, and traffic control centers.

For projects located in air quality non-attainment and maintenance areas, Congestion Mitigation and Air Quality Improvement Program (CMAQ) funds may be used for activities that demonstrate a reduction in traffic delay or emissions. CMAQ can support an individual M&O program for up to 3 years.15 Examples of projects eligible for CMAQ funds include the implementation of ITS strategies, enhanced signalization projects, and intersection improvements.

Although there are greater Federal funding opportunities for management and operations than many regions perceive, the bulk of funds typically must come from States and localities. State and local funding processes make it difficult to fully integrate planning and operations by creating separate categories of funds for capital and operations expenses.

Degrees of Funding and Resource Coordination

The structure of resource sharing arrangements may evolve over time in response to changing regional needs and changing relationships between agencies. Initially, sharing may be limited to supplying staff, equipment, or facilities in support of regional meetings or other regional collaboration activities. If appropriate, participating public and private organizations may develop more formal sharing arrangements, including pooling of funds and other resources to sustain cooperative regional efforts. In some regions, agencies may provide funding to support a regional entity charged with leading regional collaboration or an entity that owns and operates regional transportation system assets. Exhibit 9 illustrates this range of resource strategies.

Exhibit 9: Range of Resource Strategies

Exhibit 9

Source: Regional Transportation Operations Collaboration and Coordination, FHWA, 2003.

TAKING ADVANTAGE OF LINKAGE OPPORTUNITIES

All regions lack sufficient funds to implement the full spectrum of transportation projects and programs desired by the region. Sometimes, competition for resources between and within agencies can hinder regional coordination and prevent the region from achieving the full benefits of system-wide M&O strategies. This section discusses some approaches to funding and resource sharing that can help to build bridges between planning and operations practitioners.

Link Funding to Planning Goals and Objectives

Case 18: Albany New York's Funding Prioritization Process

The Capital District Transportation Commission (CDTC) is the MPO for the Albany, NY, metropolitan area. CDTC brought together a wide range of stakeholders from 1993 to 1997 to develop a new approach to long-term planning. This effort involved workshops, conferences, nine topical task forces, and a yearlong public review. The product was a more integrated approach to long-term planning and new prioritization procedures that acknowledge the importance of a variety of transportation options from management and operations strategies to TDM to smart growth.

One critical outcome of this long-range planning process was a new method for funding allocation. It defined the distribution of all regional funds among 17 project categories, consistent with the proportions agreed upon through the planning process. Projects in a given category could not be added to a new TIP if the current TIP projects exceeded the designated funding percentage for that category. This process has worked to balance the distribution of funds in a way that is more consistent with the plan's stated priorities. For example, road construction projects have consistently used more than their target share of regional dollars because of a backlog of TIP projects in this category. Consequently, no new roadway construction projects have been added to the TIP, allowing other classes of projects (such as ITS) to come closer to their target share of regional funds.

Contact John Poorman: jpoorman@cdtcmpo.org

Increasingly, local and regional transportation plans include language supporting improved transportation systems management, promoting more efficient use of existing infrastructure, and adopting a more customer-oriented approach to transportation service provision. Yet the funding and staff resources to support the implementation of such planning objectives are often lacking. For example, a plan might state that regional coordination to maximize efficiency of the existing system is a top priority, but no funding is then allocated toward regional incident management programs, corridor management strategies, or regional traveler information systems.

Several approaches have been used to more closely link funding to operations goals. One approach is to have regional stakeholders determine minimum budget requirements to support long-range transportation plan objectives in each program area (see Case 18).16 Based on these minimum requirements and total funding availability, each program area is assigned a target budget. Projects slated to receive new funding are then prioritized based on whether the target has been met for each proposed project's program area. For example, if new roadway construction is targeted to receive 40 percent of the transportation budget and the current TIP devotes 50 percent of its funding to this category, then other program categories (such as M&O) would receive higher priority when selecting projects in a new TIP.

Some regions employ a project prioritization process that deliberately assigns more weight to projects that support regional management and operations objectives, as outlined in the region's long-range plan. This approach encourages planners and operators to work together when assessing the cost-effectiveness of management and operations strategies. In these cases, the likelihood that management and operations programs receive significant funds depends on how M&O criteria are weighted relative to other prioritization criteria. At a minimum, this approach will assist stakeholders in clearly articulating where M&O investments should be positioned amongst the region's competing transportation needs.

Develop Innovative Operations Funding Sources

Case 19: Hampton Roads Region Includes ITS in Long-Range Investment Planning

The Hampton Roads region incorporated ITS into the MPO's project selection process for regional Surface Transportation Program and CMAQ funding programs. ITS projects are scored for their capacity to support planning objectives. As a result, several ITS plans and projects have been funded through this process, including a regional roadway information system, a centralized traveler information system, signal system upgrades, and implementation of the local Smart Traffic Centers. ITS is also a distinct element of the MPO's long-range plan. The current draft of the region's 2026 Plan includes long-range investments for future ITS projects.

Contact Camelia Ravanbakht: cravan@hrpdc.org

Case 20: Developers Fund Operations in Montgomery County

In Montgomery County, Maryland, an impact fee for large developments has replaced the use of some discretionary transportation funds. This new funding source has helped to promote coordination between planning and operations. The county's public works department is using these impact fees to fund operations equipment, such as monitoring cameras and signal timing improvements. In one instance, a major development funded an electronic message sign that indicates when transit parking is filled at more central rail stations, encouraging vehicles to use station parking lots located further from the region's core.

Contact Emil Wolanin: emil.wolanin@montgomerycountymd.gov


New funding mechanisms can help to create bridges between planners and operations managers. One strategy is to fund certain M&O efforts as part of the initial capital investment for a project (e.g., ITS equipment that enhances corridor management activities, see Case 19). Planners and operators increasingly see that funds for management and operations associated with a particular project or corridor are best secured in coordination allocations for major new construction or rehabilitation. Working together, planners and operators can make the case that proper management of new transportation facilities will maximize the long-term benefits of the initial investment. Some areas have required consideration of M&O by developing a checklist for project sponsors.

In the search for funding for system operations, some regions have turned to land developers. The practice of requiring developers to fund transportation improvements as a way to mitigate the transportation impacts of their projects is well established, but relying on this as a source of management and operations improvements is relatively new (see Case 20). Developer concessions can provide an important source of revenue, and can also encourage more detailed planning for management and operations programs. In order to require developer-funded improvements, local governments typically must show how the management strategies can mitigate transportation impacts, such as improvements to traffic flow in a particular corridor. This funding opportunity may also prompt local governments to more thoroughly identify management and operations needs so that individual funding opportunities can work together to support an integrated operations approach. This is critical, since operations must typically be applied on a system rather than spot location basis.

Planning and operations coordination can also be strengthened when transportation management strategies are viewed as a potential source of transportation dollars. Pricing mechanisms are an effective tool for managing transportation demand and achieving more efficient use of existing facilities. Moreover, new technologies, such as electronic toll collection, can enable greater use of pricing while reducing collection costs. They can also serve to generate funds for both management programs and new infrastructure. As such, these transportation management strategies naturally capture the interest of planners and decisionmakers, opening the window for a broader discussion between planners and operations managers.

As a first step toward incorporating some of the funding strategies such as those discussed above, examine regional planning documents for goals or objectives that support regional systems management activities. Consider how such objectives are supported with funding, performance measures, or decision criteria in the plan. Develop recommendations for future plan updates that could promote funding for management and operations objectives, such as project prioritization criteria that favor M&O strategies or multi-jurisdictional operations initiatives.

Build on Emergency Response Needs to Create Regional Momentum for Collaboration

The recent focus on improving emergency preparedness and response has heightened the need for coordination between planning and operations. Increased transportation resources are available to conduct emergency response exercises and planning. Explore these funding sources as well as opportunities to use existing emergency management activity to initiate regional interagency collaboration.

Prioritize Multi-Jurisdiction Funding Requests

Case 21: Salt Lake City Region Encourages Agency Cooperation through ITS

In the Salt Lake Region, the MPO has programmed CMAQ funds for ITS and traffic management activities. The Utah DOT, the Utah Transit Authority, and local cities and counties then work together to agree on projects to use these funds, both for capital improvements and for operating assistance. This cooperation has led to the development of one traffic management system that all play a role in and to increased interagency management and operations coordination.

Contact Doug Hattery: dhattery@wfrc.org

A number of MPOs give preference to collaborative funding requests in the project prioritization process (see Case 21). This encourages funding requests for ITS and other systems management initiatives that are coordinated between organizations and jointly submitted by different agencies and jurisdictions. Inter-jurisdictional collaboration is frequently a stated objective or strategy in regional transportation plans, so preference for these funding requests is well justified. Such coordination can help to promote a regional systems management approach.

Integrate Capital Investments and M&O Within a Single Budget Process

State and regional management and operations activities are often lumped under broad operations budget categories. These operations categories are usually assessed through a process that is separate from the capital investments planning and budget process. Where this is the case, MPOs might consider ways of incorporating specific management and operations activities as individual budget items within the capital investments budget.
Along the same lines, transportation agencies may consider addressing management and operations costs associated with a particular project as part of the capital investment decisionmaking process. This can link planning and operations by explicitly addressing M&O investments that would be required to optimally integrate the proposed project. This would provide a stronger motivation to include operators in the discussion of the M&O costs associated with capital investments. (NOTE: This discussion does not imply that routine operating costs would be supported with Federal funds.)

Share Office Facilities

Case 22: Central Ohio Regional Transportation and Emergency Management Center (CORTRAN)

In 2001 the Mid-Ohio Regional Planning Commission (MORPC) recognized the need for a multi-jurisdictional operations facility where transportation and emergency agencies work side by side to manage traffic, transit, incidents, and emergencies. MORPC conducted a feasibility and cost study, involving stakeholders in the identification of funding opportunities and in the development of an operational concept, functional requirements, and overall design of the facility. Following the study, CORTRAN evolved into a collaborative effort between State, county, and city transportation agencies, as well as emergency and public safety agencies. When the facility is finished, CORTRAN will have 50 to 60 full-time staff to control the Columbus Freeway Management System, to operate a transit computer-aided dispatching service, and to monitor video feeds of the local roads. The expected benefits of CORTRAN include improving incident management, coordinated emergency response, avoiding duplicate facilities, and providing a single source for media and communications. MORPC continues to support the CORTRAN effort by including it in the TIP with State and local funds, and by guiding the partners in forming an intergovernmental agreement.

Contact Erika Witzke: ewitzke@morpc.org

Case 23: Maricopa Association of Governments Uses the UPWP to Support M&O

Through the development of an initial regional ITS architecture, stakeholder agencies and jurisdictions in the Phoenix metropolitan area recognized the need for a Regional Concept of Transportation Operations. The Maricopa Association of Governments (MAG), the region's MPO, wanted to ensure that this M&O planning work took place in a timely fashion because it was central to ongoing M&O coordination activities. By including the Regional Concept of Transportation Operations project in MAG's UPWP, staff ensured financial support for this critical activity. The project was completed in 2003 and is the first comprehensive example in the United States for an urban transportation operations plan.

Contact Sarath Joshua: sjoshua@mag.maricopa.gov

Case 24: Examples of Using Funding to Attract Participation

  • The North Central Texas Council of Governments created training on sustainable development that incorporated management and operations priorities. The MPO used access to a new source of local matching funds as an incentive to get local jurisdiction managers to participate.

  • In order to demonstrate to public safety officials that participation in regional incident management discussions can lead to tangible results, the Maryland DOT paid for the retrofit of police facilities to accommodate Coordinated Highways Action Response Team (CHART) equipment and staff, and paid for additional State police vehicles in order to improve response times to incidents.

Case 25: Washington DOT Policy on Funding

Washington State DOT had to address a severe disparity between transportation needs and revenues in its 20-year transportation plan. The plan prioritizes investment choices as follows:

  1. Maintenance, traffic operations, and preservation activities are top priorities and are first in line for available revenues.
  2. Highway safety, environmental retrofit, economic initiatives, and a Puget Sound core system of HOV lanes are high priorities and are second in line for available revenues.
  3. Revenues remaining after the above priorities are addressed go to other highway mobility improvements.

Traffic operational solutions are considered as the first step in addressing a congestion problem identified in the plan. The stated goal of operational strategies is to reduce delay of both people and freight on the State's system. The plan defines operational strategies to include traveler information systems, safety enhancements, ramp metering in peak hours, service patrols and incident response teams, signal timing and HOV lanes, and improving advanced technology applications for commercial vehicles.

Contact Toby Rickman: Rickman@wsdot.wa.gov

Case 26: Baltimore Region Considers M&O Project Categories

Staff members for the Baltimore Regional Management and Operations Partnership submitted a traffic detection and real-time traffic operations project for consideration in a recent update of the regional transportation plan. The project did not technically fit under the capacity expansion or the maintenance and system preservation categories. Ultimately, this project was lumped together with other projects in a general TDM/TSM category. For the next plan update, the Partnership has recommended that it work with the MPO to revise project categories so M&O projects can be considered alongside traditional capital projects.

Contact Eileen Singleton: esingleton@baltometro.org

Sharing office facilities inspires enhanced collaboration. In some cases, office sharing is arranged intentionally because there is recognition that transportation agencies working in the same space may do their job more effectively (see Case 22). A common example is a traffic management center shared by traffic operators, transit staff, and public safety personnel. In this case, the planning and development of the facility functions to inform all stakeholders about the importance of regional coordination between practitioners.

At times, sharing of facilities is not by design. Groups that typically work independently may be required to share office space due to funding or facility limitations. Some agencies that have found themselves unintentionally co-located have discovered that this makes an important difference in the degree of communication between practitioners. When planners and operators are co-located, they are more likely to communicate about their projects, develop new personal relationships, and discover opportunities to assist each other.

In many cases, there is a tradition of agency and jurisdictional independence, and some practitioners may have never considered options for sharing facilities or equipment. The increased efficiency and professional ties that can grow from such cooperative arrangements suggest that this should be a more conscious part of institutional consideration.

Use the Unified Planning Work Program to Define Commitments to M&O Planning

Planning agencies continue to face the perception that management and operations planning is a secondary activity to other MPO and State DOT responsibilities. As such, when agencies are facing staffing and funding shortfalls, it can be difficult for them to initiate regional systems management activities. Some MPOs have found that specific enumeration of regional management and operations activities in the agency's Unified Planning Work Program (UPWP) is a way to ensure that such activities are implemented (see Case 23). This also builds the understanding that the MPO intends to take a leadership role on regional M&O issues.

Use Funding as a Tool to Attract Participation in M&O Discussions

Funding is a powerful tool for promoting participation. When groups are unaccustomed to coordinating with many other agencies or perceive that such coordination would provide more hardship than benefit, one way to overcome this barrier is to provide additional resources to such groups in exchange for participation in collaborative efforts. In some cases, MPOs have attempted to create training programs or other forums to promote the consideration of management and operations strategies (see Case 24). There are inevitably difficulties in getting some jurisdictions or stakeholder groups to the table, particularly when a forum or activity is not part of an established regional process. MPOs have had success in overcoming these barriers by linking participation to funding access. For example, a jurisdiction may become eligible for matching funds only by participating in a management and operations training program. Or a public safety group may gain access to new sources of funds contingent upon its participation in regional M&O forums.

LESSONS LEARNED

This section reviews some lessons learned through efforts to secure funding for M&O programs. Past experience has highlighted some of the challenges associated with using resource sharing as a means to link planning and operations, and provides insight on potential ways to overcome these challenges.

Funding Constraints Can Elevate M&O Solutions

Almost every transportation agency identifies inadequate funding as a major concern. At the same time, virtually every agency acknowledges that funding constraints are a major impetus for advancing management and operations strategies. Planners often become champions for management and operations strategies only when they recognize a serious discrepancy between available funds and the cost of new capital investments necessary to maintain regional mobility (see Case 25). This does not imply that planners should wait until desperate times before offering regional leadership on management and operations coordination, nor does this imply that practitioners should choose between funding roadway construction versus funding operational improvements. Rather, the lesson is that periods of severe funding shortfalls should be seen as opportunities to educate a broader regional constituency about management and operations solutions.

MPOs and DOTs May Resist New Operations Programs

Both MPOs and State DOTs tend to be reluctant to commit to new management and operations programs. This is generally because of the perspective that these activities are continuous and therefore commit the agency to provide funding every year or else face the unpopular option of cutting an existing program. Consequently, MPO and DOT leaders prefer that such ongoing funding requirements be left to local jurisdictions. This can create a situation in which management and operations activities are a patchwork of programs from various jurisdictions, limiting their efficiency and effectiveness at the regional scale. This lesson highlights the need for education about the value of regional operations coordination.

Perspectives Differ on the Value of Dedicated M&O Funding

Practitioners voice significantly different perspectives regarding how funding sources can best be structured to promote management and operations more consistently during the planning process. Some practitioners find that management and operations strategies are hindered by regional, State, or Federal restrictions on how particular funds can be spent. From this perspective, funding categories tend to prevent systems managers from using the most efficient approach to manage the transportation system. For example, one region maintains that ITS earmarks have been detrimental to integrated planning because they tend to set ITS on a separate track from other transportation planning activities. In some cases, this may limit exposure to ITS strategies for the planners and stakeholders who are involved in regional transportation planning.

Other practitioners have observed that the absence of funding sources specifically designated for management and operations can make it difficult to include such projects in the long-range transportation plan (see Case 26). Although M&O activities are frequently funded under broad operations or TDM categories, this often means that they are not specifically listed in the funding program. By creating more narrowly defined M&O funding categories, MPOs and State DOTs can make it clear to agencies and jurisdictions that such projects are appropriate uses for regional, State, and Federal funds. They also elevate the profile of such activities among transportation practitioners.


15 Eligibility requirements for CMAQ are listed in 23 U.S.C. 149(b).

16 Program areas include, for example, ITS, bicycle and pedestrian systems, transit programs, and roadway construction.