How to Use This Checklist

Flowchart designed as a highlevel screening tool to assess an HOV lane for conversion  to HOT.

The decision flowchart in the figure (at right) outlines a highlevel screening tool to assess your HOV lane for conversion to HOT. The Performance Considerations and Facility Considerations are reviewed first to determine if the project is technically advisable. The Institutional Considerations are then reviewed to determine if there are non-technical issues that would impact implementation and success of the project. A "No" answer to any of the factors should trigger further investigation into whether the impact can be mitigated. Any factor can become a fatal flaw if it receives a "No" depending on the unique characteristics of the individual project and community.

Performance Considerations

Agencies should consider the potential performance before adapting an HOV lane to a HOT lane. Converting an HOV lane to a HOT lane could provide significant benefits to travelers.

Factor Question Yes No
HOV Lane Utilization Will HOT lane operations remedy an existing utilization problem? Empty Cell Empty Cell
Will peak hour use remain below 1600 vehicles per hour per lane? Empty Cell Empty Cell
Will conversion have a positive impact on person throughput in the corridor? Empty Cell Empty Cell
Travel Time Will average travel-time savings be greater than 1 minute/mile and more than 5 minutes overall? Empty Cell Empty Cell
Will there be a higher reliability of travel times on the HOT lane than the general-purpose lanes? Empty Cell Empty Cell
Will the conversion create a negative impact on HOT or general-purpose lane speeds? Empty Cell Empty Cell
Will the conversion provide reliable trip times for transit? Empty Cell Empty Cell
Benefits Will the net agency/societal benefits be greater after conversions in accordance with regional goals?
(agency: toll revenue exceeds costs of conversion; societal: overall travel time savings, reduction in emissions, reduction in fuel use)
Empty Cell Empty Cell
Willingness to Pay Tolls Are there other local toll facilities that drivers are familiar with? Empty Cell Empty Cell
If so, will toll collection technology be interoperable? Empty Cell Empty Cell
Is there a market of travelers willing to pay for a higher level of service (eg, commuters, high income)? Empty Cell Empty Cell
Safety Will HOT lanes have a positive or neutral effect on the crash rate for the facility? Empty Cell Empty Cell
Environment Will conversion have a positive or neutral effect on fuel use? Empty Cell Empty Cell
Will conversion have a positive or neutral effect on emissions? Empty Cell Empty Cell
Revenue Generation Does the estimated revenue cover expected operations, maintenance and enforcement costs, and additional costs necessary for the project to be financially viable? Empty Cell Empty Cell

Tailoring the Process to Your Project

MnPass signage - Minneapolis, Minnesota

The evaluation should consider the concept of “weighting” the various screening factors based upon project objectives and regional transportation system goals. This is a subjective element that accounts for project-specific needs and conditions. All screening factors can be weighted equally, but more likely there will be certain factors that will have greater emphasis in the analysis. Based on a community’s needs and project specifics (e.g., political, public, operations, geometry), conversion may or may not be practical. The more important a factor, the greater the importance of addressing that factor should it receive a “No” answer.

Facility Considerations

Facility considerations include design, operations and enforcement features. Certain facility features are essential or desirable for successful HOT lane operation.

Factor Question Yes No
Cross Section Does the design envelope satisfy AASHTO desirable requirements for the entire length? Empty Cell Empty Cell
If not, are minimum sections less than 1000 feet in length? Empty Cell Empty Cell
Lane Separation Between HOT and General Purpose Lanes Are AASHTO guidelines satisfied for the type of separation? Empty Cell Empty Cell
Facility Access Satisfies Origin-Destination Requirements Are current access points located to serve primary users for the HOT lanes? Empty Cell Empty Cell
Facility Access Design If proposed access design is for slip ramps at grade, is buffer/barrier opening length at least 1300-1500 ft? Empty Cell Empty Cell
Is there sufficient weaving distance for vehicles to cross the general-purpose lanes and access the HOT lane without degrading freeway speed? Empty Cell Empty Cell
Ability to Enforce Are there enforcement areas included in the design of the HOT lane for detecting and detaining violators? Empty Cell Empty Cell
Is there supporting technology for enforcement? Empty Cell Empty Cell
Are current violation rates in the HOV lane < 10 percent? Empty Cell Empty Cell
Are enforcement efforts conducted on a routine basis? Empty Cell Empty Cell
Facility Traffic Control Does proposed sign placement, messaging and color conform to the MUTCD and best guidance available? Empty Cell Empty Cell
Pricing Strategy Can toll system capabilities achieve stated objectives for lane management at desired performance level of HOV and transit given geometric characteristics? Empty Cell Empty Cell
Existing Toll Technology Is there an existing tolling system in the region or state that can be leveraged for HOT operation? Empty Cell Empty Cell
Incident Management Are operational treatments for incident management available that can be provided to assure travel time reliability? Empty Cell Empty Cell
Maintenance Will the level of maintenance be adequate to ensure quality service and operations? Empty Cell Empty Cell

Institutional Considerations

Agencies must also consider the viewpoints of the public, governmental agencies, legislative authorities, the media and other stakeholders.

Factor Question Yes No
Legal Is there legislation in the state to allow for toll collection and HOT lanes? Empty Cell Empty Cell
Public Acceptance Is the public familiar with and accepting of electronic toll collection and video enforcement? Empty Cell Empty Cell
Are resources dedicated for enhanced and active public outreach and education? Empty Cell Empty Cell
Are HOV advocates amenable to changes in HOV operation? Empty Cell Empty Cell
Is the HOT concept compatible with Local and State goals and objectives? Empty Cell Empty Cell
Political Acceptance Is there a political champion? Empty Cell Empty Cell
Is there political familiarity with the HOT lanes concept? Empty Cell Empty Cell
Is there political support for the HOT lanes concept? Empty Cell Empty Cell
Is the HOT concept compatible with Local and State goals and objectives? Empty Cell Empty Cell
Environmental Justice/ Title VI Issues Are low income/minority populations disproportionately adversely affected? Empty Cell Empty Cell
Can a mitigation plan be developed if low income/minority populations are disproportionately adversely affected? Empty Cell Empty Cell
Revenue Use If net revenue use is not dictated by federal requirement, is there agreement among agencies on how net revenue will be used? Empty Cell Empty Cell
Is the public informed and accepting of proposed use of net revenue generated from the project? Empty Cell Empty Cell
Interagency Cooperation Do all transportation agencies in the corridor support the HOT lane concept? Empty Cell Empty Cell
Can operating agreements be established to specify areas of responsibility? Empty Cell Empty Cell
Is cooperation expected from the enforcement and judiciary systems? Empty Cell Empty Cell
Media Awareness Is there a positive working relationship with the media? Empty Cell Empty Cell
Are resources available to engage the media in public outreach efforts? Empty Cell Empty Cell
Project Marketing/ Evaluation Are resources dedicated to promote the project and inform the public on operating details, both before and after the ribbon cutting? Empty Cell Empty Cell
Are resources dedicated to monitor and evaluate the project after opening and to communicate ongoing performance to agency officials and the public? Empty Cell Empty Cell

For more information about implementing HOT lanes in your community, see the following resources:

FHWA Office of Operations:
https://ops.fhwa.dot.gov/freewaymgmt/index.htm

FHWA Tolling and Pricing Program:
https://ops.fhwa.dot.gov/tolling_pricing/index.htm

Neil Spiller
Transportation Specialist
Federal Highway Administration
Office of Operations, HOTM E84-431
1200 New Jersey Ave, SE
Washington D.C. 20590
Phone: 202-366-2188
neil.spiller@dot.gov
Greg Jones
Transportation Specialist
FHWA-Resource Center
61 Forsyth Street, Ste. 17T26
Atlanta, GA 30303
Phone: 404-562-3906
Fax: 404-562-3700
GregM.Jones@dot.gov

U.S. Department of Transportation - Federal Highway Administration

FHWA-HOP-12-024