Comprehensive Truck Size and Weight Limits Study: Pavement Comparative Analysis Technical Report
Appendix N: Predicted Pavement Life Cycle Costs for Flexible and Rigid Pavements
Life Cycle Cost Analyses for Each Sample Pavement Section and Each Scenario
Part 1: Using 1.9% Discount Rate
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 65,415 | 65,514 | 65,059 | 65,015 | 68,762 | 64,430 | 65,295 |
Time of Activity 1 | 31.98 | 31.96 | 32.06 | 32.07 | 31.22 | 32.21 | 32.01 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 46,781 | 46,801 | 46,707 | 46,698 | 47,467 | 46,577 | 46,756 |
Time of Activity 2 | 43.98 | 43.96 | 44.06 | 44.07 | 43.22 | 44.21 | 44.01 |
Cost 2 ($) | 43,324 | 43,488 | 42,735 | 42,662 | 48,793 | 41,688 | 43,126 |
Net Present Cost 2 ($) | 18,634 | 18,713 | 18,352 | 18,317 | 21,295 | 17,852 | 18,539 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 93,792 | 93,581 | 93,003 | 93,699 | 94,416 | 88,795 | 93,673 |
Time of Activity 1 | 26.07 | 26.11 | 26.22 | 26.09 | 25.94 | 27.03 | 26.09 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 52,401 | 52,361 | 52,251 | 52,384 | 52,528 | 51,442 | 52,379 |
Time of Activity 2 | 38.07 | 38.11 | 38.22 | 38.09 | 37.94 | 39.03 | 38.09 |
Cost 2 ($) | 85,910 | 85,622 | 84,830 | 85,784 | 86,400 | 78,976 | 85,748 |
Net Present Cost 2 ($) | 41,391 | 41,220 | 40,753 | 41,315 | 41,727 | 37,353 | 41,294 |
Time of Activity 3 | 50.07 | 50.11 | 50.22 | 50.09 | 49.94 | 51.03 | 50.09 |
Cost 3 ($) | - | - | - | - | 419 | - | - |
Net Present Cost 3 ($) | - | - | - | - | 161 | - | - |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | IRI | IRI | IRI | IRI | IRI | IRI | IRI |
IRI ($) | 41,277 | 41,384 | 41,006 | 41,277 | 41,384 | 41,277 | 41,299 |
Time of Activity 1 | 37.20 | 37.17 | 37.28 | 37.20 | 37.17 | 37.20 | 37.19 |
Cost 1 ($) | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 |
Net Present Cost 1 ($) | 39,193 | 39,216 | 39,133 | 39,193 | 39,216 | 39,193 | 39,198 |
Time of Activity 2 | 49.20 | 49.17 | 49.28 | 49.20 | 49.17 | 49.20 | 49.19 |
Cost 2 ($) | 5,356 | 5,567 | 4,822 | 5,356 | 5,567 | 5,356 | 5,400 |
Net Present Cost 2 ($) | 2,084 | 2,168 | 1,874 | $2,084 | $2,168 | 2,084 | 2,102 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | IRI | IRI | IRI | IRI | IRI | IRI | IRI |
IRI ($) | 26,091.2 | 26,122.2 | 25,590.7 | 25,492.7 | 26,226.7 | 25,590.7 | 26,037.7 |
Time of Activity 1 | 21.99 | 21.96 | 22.38 | 22.45 | 21.88 | 22.38 | 22.03 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 15,807 | 15,814 | 15,689 | 15,666 | 15,839 | 15,689 | 15,794 |
Time of Activity 2 | 36.99 | 36.96 | 37.38 | 37.45 | 36.88 | 37.38 | 37.03 |
Cost 2 ($) | 20,908 | 20,947 | 20,281 | 20,158 | 21,076 | $20,281 | 20,841 |
Net Present Cost 2 ($) | 10,284 | 10,308 | 9,902 | 9,827 | 10,388 | 9,902 | 10,243 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | IRI | IRI | IRI | IRI | IRI | IRI | IRI |
IRI ($) | 25,235 | 25,257 | 24,703 | 24,579 | 25,322 | 24,703 | 25,176 |
Time of Activity 1 | 22.66 | 22.64 | 23.08 | 23.18 | 22.59 | 23.08 | 22.70 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost ($)1 | 15,605 | 15,610 | 15,479 | 15,449 | 15,626 | 15,479 | 15,591 |
Time of Activity 2 | 37.66 | 37.64 | 38.08 | 38.18 | 37.59 | 38.08 | 37.70 |
Cost 2 ($) | 19,832 | 19,859 | 19,151 | 18,991 | 19,942 | 19,151 | 19,756 |
Net Present Cost 2 ($) | 9,630 | 9,647 | 9,224 | 9,130 | 9,697 | 9,224 | 9,585 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | IRI | IRI | IRI | IRI | IRI | IRI | IRI |
IRI ($) | 11,076 | 11,081 | 10,980 | 10,958 | 11,133 | 11,046 | 11,094 |
Time of Activity 1 | 40.53 | 40.50 | 40.98 | 41.09 | 40.26 | 40.67 | 40.44 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 11,076 | 11,081 | 10,980 | 10,958 | 11,133 | 11,046 | 11,094 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Faillure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 212,006 | 212,146 | 211,560 | 211,593 | 212,445 | 211,413 | 211,941 |
Time of Activity 1 | 6.07 | 6.05 | 6.13 | 6.13 | 6.01 | 6.15 | 6.08 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 76,905 | 76,933 | 76,815 | 76,821 | 76,994 | 76,785 | 76,892 |
Time of Activity 2 | 18.07 | 18.05 | 18.13 | 18.13 | 18.01 | 18.15 | 18.08 |
Cost 2 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 2 ($) | 61,092 | 61,114 | 61,020 | 61,025 | 61,162 | 60,996 | 61,081 |
Time of Activity 3 | 30.07 | 30.05 | 30.13 | 30.13 | 30.01 | 30.15 | 30.08 |
Cost 3 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 3 ($) | 48,530 | 48,548 | 48,473 | 48,477 | 48,586 | 48,454 | 48,522 |
Time of Activity 4 | 42.07 | 42.05 | 42.13 | 42.13 | 42.01 | 42.15 | 42.08 |
Cost 4 ($) | 57,104 | 57,242 | 56,663 | 56,695 | 57,538 | 56,516 | 57,040 |
Net Present Cost 4 ($) | 25,480 | 25,550 | 25,253 | 25,269 | 25,703 | 25,178 | 25,447 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 226,244 | 226,309 | 225,958 | 226,002 | 226,406 | 225,824 | 226,217 |
Time of Activity 1 | 4.16 | 4.16 | 4.20 | 4.20 | 4.14 | 4.22 | 4.17 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 79,767 | 79,780 | 79,710 | 79,719 | 79,799 | 79,683 | 79,762 |
Time of Activity 2 | 16.16 | 16.16 | 16.20 | 16.20 | 16.14 | 16.22 | 16.17 |
Cost 2 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 2 ($) | 63,365 | 63,376 | 63,320 | 63,327 | 63,391 | 63,299 | 63,361 |
Time of Activity 3 | 28.16 | 28.16 | 28.20 | 28.20 | 28.14 | 28.22 | 28.17 |
Cost 3 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 3 ($) | 50,336 | 50,344 | 50,300 | 50,306 | 50,357 | 50,283 | 50,333 |
Time of Activity 4 | 40.16 | 40.16 | 40.20 | 40.20 | 40.14 | 40.22 | 40.17 |
Cost 4 ($) | 70,819 | 70,881 | 70,551 | 70,592 | 70,972 | 70,425 | 70,795 |
Net Present Cost 4 ($) | 32,775 | 32,809 | 32,628 | 32,650 | 32,859 | 32,559 | 32,762 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Crack | Crack | Crack | Crack | Crack | Crack | Crack |
Crack ($) | 151,841 | 152,413 | 146,440 | 146,469 | 153,823 | 152,086 | 152,459 |
Time of Activity 1 | 14.23 | 14.13 | 15.12 | 15.12 | 13.89 | 14.19 | 14.13 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 65,765 | 65,883 | 64,646 | 64,652 | 66,188 | 65,816 | 65,893 |
Time of Activity 2 | 26.23 | 26.13 | 27.12 | 27.12 | 25.89 | 26.19 | 26.13 |
Cost 2 ($) | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 |
Net Present Cost 2 ($) | 48,373 | 48,460 | 47,549 | 47,554 | 48,684 | 48,410 | 48,467 |
Time of Activity 3 | 38.23 | 38.13 | 39.12 | 39.12 | 37.89 | 38.19 | 38.13 |
Cost 3 ($) | 78,493 | 79,117 | 72,527 | 72,560 | 80,000 | 78,760 | 79,167 |
Net Present Cost 3 ($) | 37,703 | 38,070 | 34,244 | 34,263 | 38,674 | 37,860 | 38,100 |
Time of Activity 4 | 50.23 | 50.13 | 51.12 | 51.12 | 49.89 | 50.19 | 50.13 |
Cost 4 ($) | - | - | - | - | 721 | - | - |
Net Present Cost 4 ($) | - | - | - | - | 277 | - | - |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Fault | Fault | Fault | Fault | Fault | Fault | Fault |
Fault ($) | 10,342 | 10,354 | 10,091 | 10,044 | 10,401 | 10,128 | 10,319 |
Time of Activity 1 | 44.10 | 44.04 | 45.38 | 45.63 | 43.80 | 45.19 | 44.22 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 10,342 | 10,354 | 10,091 | 10,044 | 10,401 | 10,128 | 10,319 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Fault | Fault | Fault | Fault | Fault | Fault | Fault |
Fault ($) | 19,567 | 19,588 | 18,573 | 18,362 | 19,933 | 18,748 | 19,518 |
Time of Activity 1 | 27.49 | 27.47 | 28.42 | 28.62 | 27.15 | 28.25 | 27.53 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 14,224 | 14,229 | 13,973 | 13,919 | 14,316 | 14,017 | 14,212 |
Time of Activity 2 | 42.49 | 42.47 | 43.42 | 43.62 | 42.15 | 43.25 | 42.53 |
Cost 2 ($) | 12,071 | 12,101 | 10,580 | 10,257 | 12,609 | 10,845 | 11,999 |
Net Present Cost 2 ($) | 5,343 | 5,358 | 4,600 | 4,443 | 5,617 | 4,731 | 5,306 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Fault | Fault | Fault | Fault | Fault | Fault | Fault |
Fault ($) | 15,521 | 15,505 | 14,875 | 14,679 | 15,941 | 15,444 | 15,745 |
Time of Activity 1 | 31.45 | 31.47 | 32.13 | 32.34 | 31.02 | 31.53 | 31.22 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 13,182 | 13,178 | 13,011 | 12,959 | 13,293 | 13,162 | 13,242 |
Time of Activity 2 | 46.45 | 46.47 | 47.13 | 47.34 | 46.02 | 46.53 | 46.22 |
Cost 2 ($) | 5,700 | 5,675 | 4,605 | 4,267 | 6,401 | 5,572 | 6,076 |
Net Present Cost 2 ($) | 2,338 | 2,327 | 1,864 | 1,721 | 2,648 | 2,282 | 2,504 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Faillure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 147,816 | 152,197 | 146,819 | 146,930 | 152,351 | 147,898 | 147,557 |
Time of Activity 1 | 15.95 | 15.25 | 16.11 | 16.09 | 15.22 | 15.93 | 15.99 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 63,630 | 64,492 | 63,433 | 63,455 | 64,522 | 63,646 | 63,579 |
Time of Activity 2 | 27.95 | 27.25 | 28.11 | 28.09 | 27.22 | 27.93 | 27.99 |
Cost 2 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 2 ($) | 50,546 | 51,231 | 50,390 | 50,407 | 51,255 | 50,559 | 50,506 |
Time of Activity 3 | 39.95 | 39.25 | 40.11 | 40.09 | 39.22 | 39.93 | 39.99 |
Cost 3 ($) | 72,384 | 77,435 | 71,220 | 71,350 | 77,609 | 72,480 | 72,082 |
Net Present Cost 3 ($) | 33,639 | 36,474 | 32,996 | 33,068 | 36,573 | 33,693 | 33,472 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Faillure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 97,792 | 92,557 | 93,686 | 93,939 | 98,115 | 97,820 | 88,703 |
Time of Activity 1 | 25.21 | 26.30 | 26.09 | 26.04 | 25.14 | 25.21 | 27.05 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 53,269 | 52,165 | 52,381 | 52,429 | 53,339 | 53,275 | 51,424 |
Time of Activity 2 | 37.21 | 38.30 | 38.09 | 38.04 | 37.14 | 37.21 | 39.05 |
Cost 2 ($) | 86,400 | 84,216 | 85,765 | 86,112 | 86,400 | 86,400 | 78,846 |
Net Present Cost 2 ($) | 42,316 | 40,391 | 41,305 | 41,510 | 42,372 | 42,321 | 37,278 |
Time of Activity 3 | 49.21 | 50.30 | 50.09 | 50.04 | 49.14 | 49.21 | 51.05 |
Cost 3 ($) | 5,674 | - | - | - | 6,170 | 5,717 | - |
Net Present Cost 3 ($) | 2,208 | - | - | - | 2,404 | 2,224 | - |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | IRI | IRI | IRI | IRI | IRI | IRI | IRI |
IRI ($) | 35,926 | 35,933 | 35,896 | 35,915 | 35,933 | 35,933 | 35,933 |
Time of Activity 1 | 41.73 | 41.72 | 41.78 | 41.75 | 41.72 | 41.72 | 41.72 |
Cost 1 ($) | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 |
Net Present Cost 1 ($) | 35,926 | 35,933 | 35,896 | 35,915 | 35,933 | 35,933 | 35,933 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | IRI | IRI | IRI | IRI | IRI | IRI | IRI |
IRI ($) | 22,113 | 22,148 | 21,251 | 21,066 | 22,322 | 22,143 | 22,049 |
Time of Activity 1 | 25.23 | 25.20 | 25.97 | 26.14 | 25.05 | 25.20 | 25.28 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 14,855 | 14,863 | 14,643 | 14,597 | 14,905 | 14,862 | 14,839 |
Time of Activity 2 | 40.23 | 40.20 | 40.97 | 41.14 | 40.05 | 40.20 | 40.28 |
Cost 2 ($) | 15,703 | 15,751 | 14,502 | 14,241 | 15,990 | 15,744 | 15,615 |
Net Present Cost 2 ($) | 7,259 | 7,285 | 6,608 | 6,469 | 7,417 | 7,281 | 7,210 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | IRI | IRI | IRI | IRI | IRI | IRI | IRI |
IRI ($) | 13,626 | 13,640 | 12,809 | 12,592 | 13,694 | 13,603 | 13.563 |
Time of Activity 1 | 33.50 | 33.48 | 34.43 | 34.68 | 33.42 | 33.52 | 33.57 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 12,675 | 12,679 | 12,451 | 12,392 | 12,693 | 12,669 | 12.657 |
Time of Activity 2 | 48.50 | 48.48 | 49.43 | 49.68 | 48.42 | 48.52 | 48.57 |
Cost 2 ($) | 2,414 | 2,438 | 923 | 519 | 2,534 | 2,371 | 2,298 |
Net Present Cost 2 ($) | 951 | 962 | 358 | 200 | 1,001 | 935 | 905 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | None | None | None | None | None | None | None |
Cost ($) | - | - | - | - | - | - | - |
Time of Activity 1 | > 50 | > 50 | > 50 | > 50 | > 50 | > 50 | > 50 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 197,059 | 197,271 | 196,489 | 197,006 | 197,422 | 196,763 | 196,988 |
Time of Activity 1 | 8.18 | 8.15 | 8.27 | 8.19 | 8.13 | 8.23 | 8.19 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 73,849 | 73,892 | 73,731 | 73,838 | 73,924 | 73,788 | 73,834 |
Time of Activity 2 | 20.18 | 20.15 | 20.27 | 20.19 | 20.13 | 20.23 | 20.19 |
Cost 2 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 2 ($) | 58,664 | 58,699 | 58,570 | 58,655 | 58,723 | 58,615 | 58,652 |
Time of Activity 3 | 32.18 | 32.15 | 32.27 | 32.19 | 32.13 | 32.23 | 32.19 |
Cost 3 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 3 ($) | 46,601 | 46,629 | 46,527 | 46,594 | 46,649 | 46,563 | 46,592 |
Time of Activity 4 | 44.18 | 44.15 | 44.27 | 44.19 | 44.13 | 44.23 | 44.19 |
Cost 4 ($) | 41,883 | 42,106 | 41,285 | 41,827 | 42,264 | 41,573 | 41,809 |
Net Present Cost 4 ($) | 17,945 | 18,051 | 17,661 | 17,919 | 18,127 | 17,798 | 17,910 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 219,462 | 219,587 | 219,245 | 219,447 | 219,645 | 219,329 | 219,429 |
Time of Activity 1 | 5.06 | 5.04 | 5.09 | 5.06 | 5.03 | 5.08 | 5.06 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 78,409 | 78,434 | 78,366 | 78,406 | 78,446 | 78,383 | 78,403 |
Time of Activity 2 | 17.06 | 17.04 | 17.09 | 17.06 | 17.03 | 17.08 | 17.06 |
Cost 2 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 2 ($) | 62,287 | 62,307 | 62,252 | 62,284 | 62,316 | 62,266 | 62,282 |
Time of Activity 3 | 29.06 | 29.04 | 29.09 | 29.06 | 29.03 | 29.08 | 29.06 |
Cost 3 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 3 ($) | 49,479 | 49,495 | 49,452 | 49,478 | 49,503 | 49,463 | 49,475 |
Time of Activity 4 | 41.06 | 41.04 | 41.09 | 41.06 | 41.03 | 41.08 | 41.06 |
Cost 4 ($) | 64,376 | 64,496 | 64,167 | 64,362 | 64,552 | 64,248 | 64,344 |
Net Present Cost 4 ($) | 29,286 | 29,350 | 29,175 | 29,279 | 29,380 | 29,218 | 29,269 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Crack | Crack | Crack | Crack | Crack | Crack | Crack |
Crack ($) | 110,491 | 113,186 | 103,331 | 103,679 | 116,695 | 112,386 | 113,264 |
Time of Activity 1 | 21.77 | 21.22 | 23.27 | 23.19 | 20.52 | 21.29 | 21.21 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 56,907 | 57,507 | 55,296 | 55,375 | 58,282 | 57,429 | 57,524 |
Time of Activity 2 | 33.77 | 33.22 | 35.27 | 35.19 | 32.52 | 33.29 | 33.21 |
Cost 2 ($) | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 |
Net Present Cost 2 ($) | 41,857 | 42,298 | 40,672 | 40,730 | 42,869 | 42,241 | 42,311 |
Time of Activity 3 | 45.77 | 45.22 | 47.27 | 47.19 | 44.52 | 45.29 | 45.21 |
Cost 3 ($) | 28,215 | 31,859 | 18,232 | 18,728 | 36,514 | 31,388 | 31,963 |
Net Present Cost 3 ($) | 11,727 | 13,381 | 7,363 | 7,574 | 15,543 | 13,166 | 13,429 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | None | None | None | None | None | None | None |
Cost ($) | - | - | - | - | - | - | - |
Time of Activity 1 | > 50 | > 50 | > 50 | > 50 | > 50 | > 50 | > 50 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | None | None | None | None | None | None | None |
Cost ($) | - | - | - | - | - | - | - |
Time of Activity 1 | > 50 | > 50 | > 50 | > 50 | > 50 | > 50 | > 50 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Crack | Crack | Crack | Crack | Crack | Crack | Crack |
Crack ($) | 99,701 | 103,677 | 92,775 | 91,440 | 108,520 | 103,475 | 104,127 |
Time of Activity 1 | 19.69 | 18.79 | 21.31 | 21.63 | 17.73 | 18.84 | 18.69 |
Cost 1 ($) | 68,400 | 68,400 | 68,400 | 68,400 | 68,400 | 68,400 | 68,400 |
Net Present Cost 1 ($) | 46,887 | 47,700 | 45,452 | 45,172 | 48,680 | 47,659 | 47,791 |
Time of Activity 2 | 31.69 | 30.79 | 33.31 | 33.63 | 29.73 | 30.84 | 30.69 |
Cost 2 ($) | 68,400 | 68,400 | 68,400 | 68,400 | 68,400 | 68,400 | 68,400 |
Net Present Cost 2 ($) | 37,264 | 37,892 | 36,106 | 35,884 | 38,670 | 37,859 | 37,965 |
Time of Activity 3 | 43.69 | 42.79 | 45.31 | 45.63 | 41.73 | 42.84 | 42.69 |
Cost 3 ($) | 35,990 | 41,097 | 26,752 | 24,918 | 47,139 | 40,841 | 41,667 |
Net Present Cost 3 ($) | 15,568 | 18,085 | 11,218 | 10,384 | 21,170 | 17,957 | 18,371 |
Scenario | 1 | 2 | 3 | 4 | 5 | 6 |
---|---|---|---|---|---|---|
Weighted Average % Change in LCC | +0.4 | -2.4 | -2.6 | +1.8 | +0.1 | +0.1 |
Life Cycle Cost Analyses for Each Sample Pavement Section and Each Scenario
Part 2: Using 7.0% Discount Rate
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Faioure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 10,263 | 10,286 | 10,178 | 10,167 | 11,082 | 10,029 | 10,234 |
Time of Activity 1 | 31.98 | 31.96 | 32.06 | 32.07 | 31.22 | 32.21 | 32.01 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 8,482 | 8,496 | 8,432 | 8,426 | 8,963 | 8,344 | 8,465 |
Time of Activity 2 | 43.98 | 43.96 | 44.06 | 44.07 | 43.22 | 44.21 | 44.01 |
Cost 2 ($) | 43,324 | 43,488 | 42,735 | 42,662 | 48,793 | 41,688 | 43,126 |
Net Present Cost 2 ($) | 1,780 | 1,790 | 1,746 | 1,742 | 2,119 | 1,685 | 1,769 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 18,453 | 18,381 | 18,185 | 18,421 | 18,665 | 16,799 | 18,412 |
Time of Activity 1 | 26.07 | 26.11 | 26.22 | 26.09 | 25.94 | 27.03 | 26.09 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 13,029 | 12,992 | 12,888 | 13,013 | 13,149 | 12,150 | 13,008 |
Time of Activity 2 | 38.07 | 38.11 | 38.22 | 38.09 | 37.94 | 39.03 | 38.09 |
Cost 2 ($) | 85,910 | 85,622 | 84,830 | 85,784 | 86,400 | 78,976 | 85,748 |
Net Present Cost 2 ($) | 5,423 | 5,389 | 5,297 | 5,408 | 5,504 | 4,649 | 5,404 |
Time of Activity 3 | 50.07 | 50.11 | 50.22 | 50.09 | 49.94 | 51.03 | 50.09 |
Cost 3 ($) | - | - | - | - | 419 | - | - |
Net Present Cost 3 ($) | - | - | - | - | 11 | - | - |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | IRI | IRI | IRI | IRI | IRI | IRI | IRI |
IRI | 5,530 | 5,549 | 5,484 | 5,530 | 5,549 | 5,530 | 5,534 |
Time of Activity 1 | 37.20 | 37.17 | 37.28 | 37.20 | 37.17 | 37.20 | 37.19 |
Cost 1 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 |
Net Present Cost 1 | 5,380 | 5,392 | 5,349 | 5,380 | 5,392 | 5,380 | 5,382 |
Time of Activity 2 | 49.20 | 49.17 | 49.28 | 49.20 | 49.17 | 49.20 | 49.19 |
Cost 2 | 5,356 | 5,567 | 4,822 | 5,356 | 5,567 | 5,356 | 5,400 |
Net Present Cost 2 | 151 | 157 | 135 | 151 | 157 | 151 | 152 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | IRI | IRI | IRI | IRI | IRI | IRI | IRI |
IRI ($) | 6,314.8 | 6,328.4 | 6,096.9 | 6,054.8 | 6,054.8 | 6,096.9 | 6,291.3 |
Time of Activity 1 | 21.99 | 21.96 | 22.38 | 22.45 | 21.88 | 22.38 | 22.03 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 4,887 | 4,896 | 4,751 | 4,724 | 4,925 | 4,751 | 4,873 |
Time of Activity 2 | 36.99 | 36.96 | 37.38 | 37.45 | 36.88 | 37.38 | 37.03 |
Cost 2 ($) | 20,908 | 20,947 | 20,281 | 20,158 | 21,076 | 20,281 | 20,841 |
Net Present Cost 2 ($) | 1,428 | 1,433 | 1,346 | 1,330 | 1,450 | 1,346 | 1,419 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | IRI | IRI | IRI | IRI | IRI | IRI | IRI |
IRI ($) | 5,945 | 5,954 | 5,722 | 5,671 | 5,982 | 5,722 | 5,920 |
Time of Activity 1 | 22.66 | 22.64 | 23.08 | 23.18 | 22.59 | 23.08 | 22.70 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 4,655 | 4,661 | 4,514 | 4,482 | 4,679 | $4,514 | 4,639 |
Time of Activity 2 | 37.66 | 37.64 | 38.08 | 38.18 | 37.59 | 38.08 | 37.70 |
Cost 2 ($) | 19,832 | 19,859 | 19,151 | 18,991 | 19,942 | 19,151 | $19,756 |
Net Present Cost 2 ($) | 1,290 | 1,293 | 1,208 | 1,189 | 1,304 | 1,208 | 1,280 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | IRI | IRI | IRI | IRI | IRI | IRI | IRI |
IRI ($) | 1,273 | 1,275 | 1,231 | 1,222 | 1,298 | 1,260 | 1,281 |
Time of Activity 1 | 40.53 | 40.50 | 40.98 | 41.09 | 40.26 | 40.67 | 40.44 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 1,273 | 1,275 | 1,231 | 1,222 | 1,298 | 1,260 | 1,281 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 91,346 | 91,480 | 90,920 | 90,951 | 91,767 | 90,779 | 91,285 |
Time of Activity 1 | 6.07 | 6.05 | 6.13 | 6.13 | 6.01 | 6.15 | 6.08 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | $86,400 | 86,400 | 86,400 | $86,400 |
Net Present Cost 1 ($) | 55,621 | 55,699 | 55,374 | 55,392 | 55,865 | 55,293 | 55,585 |
Time of Activity 2 | 18.07 | 18.05 | 18.13 | 18.13 | 18.01 | 18.15 | 18.08 |
Cost 2 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 2 ($) | 23,283 | 23,315 | 23,180 | 23,187 | 23,385 | 23,145 | 23,268 |
Time of Activity 3 | 30.07 | 30.05 | 30.13 | 30.13 | 30.01 | 30.15 | 30.08 |
Cost 3 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 3 ($) | 9,746 | 9,760 | 9,703 | 9,706 | 9,789 | 9,689 | 9,740 |
Time of Activity 4 | 42.07 | 42.05 | 42.13 | 42.13 | 42.01 | 42.15 | 42.08 |
Cost 4 ($) | 57,104 | 57,242 | 56,663 | $56,695 | 57,538 | 56,516 | 57,040 |
Net Present Cost 4 ($) | 2,696 | 2,707 | 2,664 | 2,666 | 2,729 | 2,653 | 2,692 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 105,632 | 105,701 | 105,332 | 105,379 | 105,803 | 105,193 | 105,605 |
Time of Activity 1 | 4.16 | 4.16 | 4.20 | 4.20 | 4.14 | 4.22 | 4.17 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 63,867 | 63,907 | 63,694 | 63,721 | 63,965 | 63,614 | 63,851 |
Time of Activity 2 | 16.16 | 16.16 | 16.20 | 16.20 | 16.14 | 16.22 | 16.17 |
Cost 2 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 2 ($) | 26,735 | 26,751 | 26,662 | 26,673 | 26,776 | 26,629 | 26,728 |
Time of Activity 3 | 28.16 | 28.16 | 28.20 | 28.20 | 28.14 | 28.22 | 28.17 |
Cost 3 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 3 ($) | 11,191 | 11,198 | 11,161 | $11,165 | 11,208 | 11,147 | 11,188 |
Time of Activity 4 | 40.16 | 40.16 | 40.20 | 40.20 | 40.14 | 40.22 | 40.17 |
Cost 4 ($) | 70,819 | 70,881 | 70,551 | 70,592 | 70,972 | 70,425 | 70,795 |
Net Present Cost 4 ($) | 3,840 | 3,845 | 3,815 | 3,819 | $3,854 | 3,803 | 3,837 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Crack | Crack | Crack | Crack | Crack | Crack | Crack |
Crack ($) | 47,597 | 47,960 | 44,255 | 44,273 | 48,881 | 7,752 | 47,990 |
Time of Activity 1 | 14.23 | 14.13 | 15.12 | 15.12 | 13.89 | 14.19 | 14.13 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 30,772 | 30,981 | 28,837 | 28,847 | 31,527 | 30,861 | 30,998 |
Time of Activity 2 | 26.23 | 26.13 | 27.12 | 27.12 | 25.89 | 26.19 | 26.13 |
Cost 2 ($) | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 |
Net Present Cost 2 ($) | 11,927 | 12,008 | 11,177 | 11,181 | 12,220 | 11,961 | 12,015 |
Time of Activity 3 | 38.23 | 38.13 | 39.12 | 39.12 | 37.89 | 38.19 | 38.13 |
Cost 3 ($) | 78,493 | 79,117 | 72,527 | 72,560 | 80,000 | 78,760 | 79,167 |
Net Present Cost 3 ($) | 4,898 | 4,971 | 4,242 | 4,245 | 5,115 | 4,929 | 4,977 |
Time of Activity 4 | 50.23 | 50.13 | 51.12 | 51.12 | 49.89 | 50.19 | 50.13 |
Cost 4 ($) | - | - | - | - | 721 | - | - |
Net Present Cost 4 ($) | - | - | - | - | 277 | - | - |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Fault | Fault | Fault | Fault | Fault | Fault | Fault |
Fault ($) | 982 | 986 | 895 | 879 | 1,003 | 907 | 974 |
Time of Activity 1 | 44.10 | 44.04 | 45.38 | 45.63 | 43.80 | 45.19 | 44.22 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 982 | 986 | 895 | 879 | 1,003 | 907 | 974 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Fault | Fault | Fault | Fault | Fault | Fault | Fault |
Fault ($) | 3,832 | 3,838 | 3,518 | 3,454 | 3,951 | 3,572 | 3,816 |
Time of Activity 1 | 27.49 | 27.47 | 28.42 | 28.62 | 27.15 | 28.25 | 27.53 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 3,279 | 3,283 | 3,065 | 3,021 | 3,359 | 3,102 | 3,268 |
Time of Activity 2 | 42.49 | 42.47 | 43.42 | 43.62 | 42.15 | 43.25 | 42.53 |
Cost 2 ($) | 12,071 | 12,101 | 10,580 | 10,257 | 12,609 | 10,845 | 11,999 |
Net Present Cost 2 ($) | 553 | 555 | 453 | 433 | 592 | 470 | 548 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Fault | Fault | Fault | Fault | Fault | Fault | Fault |
Fault ($) | 2,655 | 2,651 | 2,491 | $2,442 | 2,765 | 2,635 | 2,713 |
Time of Activity 1 | 31.45 | 31.47 | 32.13 | 32.34 | 31.02 | 31.53 | 31.22 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 2,459 | 2,456 | 2,340 | 2,305 | 2,538 | 2,445 | 2,501 |
Time of Activity 2 | 46.45 | 46.47 | 47.13 | 47.34 | 46.02 | 46.53 | 46.22 |
Cost 2 ($) | 5,700 | 5,675 | 4,605 | 4,267 | 6,401 | 5,572 | 6,076 |
Net Present Cost 2 ($) | 196 | 195 | 151 | 137 | 227 | 190 | 212 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 42,515 | 45,029 | 41,956 | 42,018 | 45,118 | $42,562 | 42,370 |
Time of Activity 1 | 15.95 | 15.25 | 16.11 | 16.09 | 15.22 | 15.93 | 15.99 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 27,160 | 28,578 | 26,843 | 26,878 | 28,628 | 27,186 | 27,077 |
Time of Activity 2 | 27.95 | 27.25 | 28.11 | 28.09 | 27.22 | 27.93 | 27.99 |
Cost 2 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 2 ($) | 11,369 | 11,963 | 11,236 | 11,251 | 11,984 | 11,380 | 11,334 |
Time of Activity 3 | 39.95 | 39.25 | 40.11 | 40.09 | 39.22 | 39.93 | 39.99 |
Cost 3 ($) | 72,384 | 77,435 | 71,220 | 71,350 | 77,609 | 72,480 | 72,082 |
Net Present Cost 3 ($) | 3,987 | 4,488 | 3,877 | 3,889 | 4,506 | 3,996 | 3,958 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 19,828 | 18,035 | 18,417 | 18,503 | 19,941 | 19,838 | 16,769 |
Time of Activity 1 | 25.21 | 26.30 | 26.09 | 26.04 | 25.14 | 25.21 | 27.05 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 13,865 | 12,809 | 13,010 | 13,056 | $13,934 | 13,871 | 12,134 |
Time of Activity 2 | 37.21 | 38.30 | 38.09 | 38.04 | 37.14 | 37.21 | 39.05 |
Cost 2 ($) | 86,400 | 84,216 | 85,765 | 86,112 | 86,400 | 86,400 | 78,846 |
Net Present Cost 2 ($) | 5,804 | 5,226 | 5,406 | 5,447 | 5,833 | 5,806 | 4,635 |
Time of Activity 3 | 49.21 | 50.30 | 50.09 | 50.04 | 49.14 | 49.21 | 51.05 |
Cost 3 ($) | 5,674 | - | - | - | 6,170 | 5,717 | - |
Net Present Cost 3 ($) | 160 | - | - | - | 174 | 161 | - |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | IRI | IRI | IRI | IRI | IRI | IRI | IRI |
IRI ($) | 3,870 | 3,873 | 3,858 | 3,866 | 3,873 | 3,873 | 3,873 |
Time of Activity 1 | 41.73 | 41.72 | 41.78 | 41.75 | 41.72 | 41.72 | 41.72 |
Cost 1 ($) | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 |
Net Present Cost 1 ($) | 3,870 | 3,873 | 3,858 | 3,866 | 3,873 | 3,873 | 3,873 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | IRI | IRI | IRI | IRI | IRI | IRI | IRI |
IRI ($) | 4,711 | 4,724 | 4,401 | 4,336 | 4,788 | 4,722 | 4,687 |
Time of Activity 1 | 25.23 | 25.20 | 25.97 | 26.14 | 25.05 | 25.20 | 25.28 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 3,863 | 3,872 | 3,659 | 3,616 | 3,914 | 3,871 | 3,848 |
Time of Activity 2 | 40.23 | 40.20 | 40.97 | 41.14 | 40.05 | 40.20 | 40.28 |
Cost 2 ($) | 15,703 | 15,751 | 14,502 | 14,241 | 15,990 | $15,744 | 15,615 |
Net Present Cost 2 ($) | 848 | 852 | 741 | 720 | 874 | 851 | 839 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | IRI | IRI | IRI | IRI | IRI | IRI | IRI |
IRI ($) | 2,191 | 2,194 | 2,007 | 1,960 | 2,207 | 2,186 | 2,176 |
Time of Activity 1 | 33.50 | 33.48 | 34.43 | 34.68 | 33.42 | 33.52 | 33.57 |
Cost 1 ($) | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 | 24,100 |
Net Present Cost 1 ($) | 2,119 | 2,112 | 1,982 | 1,946 | 2,131 | 2,116 | 2,109 |
Time of Activity 2 | 48.50 | 48.48 | 49.43 | 49.68 | 48.42 | 48.52 | 48.57 |
Cost 2 ($) | 2,412 | 2,438 | 923 | 519 | 2,534 | 2,371 | 2,298 |
Net Present Cost 2 ($) | 71 | 72 | 26 | 14 | 75 | 70 | 68 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | None | None | None | None | None | None | None |
Cost ($) | - | - | - | - | - | - | - |
Time of Activity 1 | >50 | >50 | >50 | >50 | >50 | >50 | >50 |
Scenarios | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 77,738 | 77,922 | 77,247 | 77,692 | 78,053 | 77,483 | 77,677 |
Time of Activity 1 | 8.18 | 8.15 | 8.27 | 8.19 | 8.13 | 8.23 | 8.19 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 47,710 | 47,817 | 47,424 | 47,684 | 47,894 | 47,561 | 47,675 |
Time of Activity 2 | 20.18 | 20.15 | 20.27 | 20.19 | 20.13 | 20.23 | 20.19 |
Cost 2 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 2 ($) | 19,971 | 20,016 | 19,851 | 19,960 | 20,048 | 19,909 | 19,956 |
Time of Activity 3 | 32.18 | 32.15 | 32.27 | 32.19 | 32.13 | 32.23 | 32.19 |
Cost 3 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 3 ($) | 8,360 | 8,379 | 8,310 | 8,355 | 8,392 | 8,334 | 8,354 |
Time of Activity 4 | 44.18 | 44.15 | 44.27 | 44.19 | 44.13 | 44.23 | 44.19 |
Cost 4 ($) | 41,883 | 42,106 | 41,285 | 41,827 | 42,264 | 41,573 | 41,809 |
Net Present Cost 4 ($) | 1,696 | 1,709 | 1,662 | 1,693 | 1,718 | 1,679 | 1,692 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Rut | Rut | Rut | Rut | Rut | Rut | Rut |
Rut ($) | 98,663 | 98,788 | 98,445 | 98,648 | 98,847 | 98,529 | 98,629 |
Time of Activity 1 | 5.06 | 5.04 | 5.09 | 5.06 | 5.03 | 5.08 | 5.06 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 1 ($) | 59,851 | 59,924 | 59,725 | 59,843 | 59,957 | 59,774 | 59,832 |
Time of Activity 2 | 17.06 | 17.04 | 17.09 | 17.06 | 17.03 | 17.08 | 17.06 |
Cost 2 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 2 ($) | 25,053 | 25,084 | 25,001 | 25,050 | 25,098 | 25,021 | 25,045 |
Time of Activity 3 | 29.06 | 29.04 | 29.09 | 29.06 | 29.03 | 29.08 | 29.06 |
Cost 3 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net Present Cost 3 ($) | 10,487 | 10,500 | 10,465 | 10,486 | 10,506 | 10,474 | 10,484 |
Time of Activity 4 | 41.06 | 41.04 | 41.09 | 41.06 | 41.03 | 41.08 | 41.06 |
Cost 4 ($) | 64,376 | 64,496 | 64,167 | 64,362 | 64,552 | 64,248 | 64,344 |
Net Present Cost 4 ($) | 3,271 | 3,281 | 3,253 | 3,270 | 3,286 | 3,260 | 3,268 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Crack | Crack | Crack | Crack | Crack | Crack | Crack |
Crack ($) | 25,720 | 26,897 | 22,748 | 22,887 | 28,480 | 26,742 | 26,932 |
Time of Activity 1 | 21.77 | 21.22 | 23.27 | 23.19 | 20.52 | 21.29 | 21.21 |
Cost 1 ($) | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 | 86,400 |
Net present Cost 1 ($) | 17,802 | 18,522 | 15,968 | 16,055 | 19,485 | 18,427 | 18,543 |
Time of Activity 2 | 33.77 | 33.22 | 35.27 | 35.19 | 32.52 | 33.29 | 33.21 |
Cost 2 ($) | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 | 80,000 |
Net Present Cost 2 ($) | 6,900 | 7,179 | 6,189 | 6,223 | 7,552 | 7,142 | 7,187 |
Time of Activity 3 | 45.77 | 45.22 | 47.27 | 47.19 | 44.52 | 45.29 | 45.21 |
Cost 3 ($) | 28,215 | 31,859 | 18,232 | 18,728 | 36,514 | 31,388 | 31,963 |
Net Present Cost 3 ($) | 1,019 | 1,197 | 590 | 610 | 1,443 | 1,173 | 1,202 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failulre Mode: | None | None | None | None | None | None | None |
Cost ($) | - | - | - | - | - | - | - |
Time of Activity 1 | >50 | >50 | >50 | >50 | >50 | >50 | >50 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | None | None | None | None | None | None | None |
Cost ($) | - | - | - | - | - | - | - |
Time of Activity 1 | >50 | >50 | >50 | >50 | >50 | >50 | >50 |
Scenarios: | Base | Scenario 1 | Scenario 2 | Scenario 3 | Scenario 4 | Scenario 5 | Scenario 6 |
---|---|---|---|---|---|---|---|
Failure Mode: | Crack | Crack | Crack | Crack | Crack | Crack | Crack |
Crack ($) | 24,764 | 26,656 | 21,671 | 21,104 | 29,080 | 26,558 | 26,876 |
Time of Activity 1 | 19.69 | 18.79 | 21.31 | 21.63 | 17.73 | 18.84 | 18.69 |
Cost 1 ($) | 68,400 | 68,400 | 68,400 | 68,400 | 68,400 | 68,400 | 68,400 |
Net Present Cost 1 ($) | 16,391 | 17,492 | 14,572 | 14,236 | 18,891 | 17,435 | 17,620 |
Time of Activity 2 | 31.69 | 30.79 | 33.31 | 33.63 | 29.73 | 30.84 | 30.69 |
Cost 2 ($) | 68,400 | 68,400 | 68,400 | 68,400 | 68,400 | 68,400 | 68,400 |
Net Present Cost 2 ($) | 6,861 | 7,322 | 6,100 | 5,959 | 7,908 | 7,298 | 7,376 |
Time of Activity 3 | 43.69 | 42.79 | 45.31 | 45.63 | 41.73 | 42.84 | 42.69 |
Cost 3 ($) | 35,990 | 41,097 | 26,752 | 24,918 | 47,139 | 40,841 | 41,667 |
Net Present Cost 3 ($) | 1,511 | 1,842 | 999 | 909 | 2,281 | 1,824 | 1,881 |
Scenario | 1 | 2 | 3 | 4 | 5 | 6 |
---|---|---|---|---|---|---|
Weighted Average % Change in LCC | +0.7 | -4.2 | -4.1 | +2.7 | +0.2 | +0.2 |