Description of Figure
3-7. CHART II Change Control Process
This figure shows the change control process flow for the CHART II project.
The originator proposes a system change to the project manager. The project
manager evaluates the proposed change to determine which level of review
(A or B) it should receive, and routes it through the CMO. The CMO enters
all proposed changes into the appropriate CM tool, and updates the change
status throughout the process. The CMO either sends the change to the
designated reviewer, or returns it to the originator. The reviewers return
their results to the CMO, who then sends the change to the final approval
authority (CCB for level A, PRB for level B), who either approves, rejects
or defers the change and notifies the CMO. For those changes that are
approved, the CMO sends notification to the change implementer to make
the change. The implementer then notifies the CMO when the change is complete.
|