Project Name

ND’s Bridge Load Testing Project

Eligible Entity Applying to Receive Federal Funding

NDDOT

Total Project Cost

$2,654,000

ATCMTD Request $1,327,000
Are matching funds restricted to a specific project component? If so, which one?

No

State(s) in which the project is located

North Dakota

Is the project currently programmed in the:
  • Transportation Improvement Program (TIP)
  • Statewide Transportation Improvement Program (STIP)
  • MPO Long Range Transportation Plan
  • State Long Range Transportation Plan

No
No
No
No

Technologies Proposed to Be Deployed (briefly list)

Diagnostic load testing technology and Non-Destructive Evaluation using strain transducers, deflection sensors, and tiltmeter rotation sensors.