Attachment B - Project Schedule

SPaT Deployment

Estimated
Start Date

Estimated
End Date

Notes

Feasibility Study

12/2017

1/2018

 

No Value

Environmental

4/2018

4/2019

No Value

Design – Plans, Specifications
and Estimates (PS&E)

4/2018

4/2019

Multi-phase

Construction

5/2019

9/2021

Multi-phase

 

Communication Gap Closure

Estimated
Start Date

Estimated
End Date

Notes

Feasibility Study

12/2017

1/2018

No Value

Environmental

4/2018

4/2019

No Value

Design Plans, Specifications and Estimates (PS&E)

4/2018

4/2019

Multi-phase

Construction

5/2019

9/2021

Multi-phase

 

Signal Synchronization and Timing

Estimated
Start Date

Estimated
End Date

No Value

Feasibility Study

N/A

N/A

No Value

Environmental

4/2018

4/2020

No Value

Design Plans, Specifications and Estimates (PS&E)

4/2018

3/2020

Multi-phase

Construction

5/2019

9/2021

Multi-phase

 

Upgraded Traffic Signal Controller and Firmware Integration

Estimated Start Date

Estimated End Date

No Value

Feasibility Study

N/A

N/A

No Value

Environmental

4/2018

4/2019

No Value

Design – Plans, Specifications
and Estimates (PS&E)

12/2017

1/2020

Multi-phase

Construction

5/2019

9/2021

Multi-phase

 

Pedestrian Safety Measures /Bluetooth/Wi-Fi Reader Deployment

Estimated Start Date

Estimated End Date

No Value

Feasibility Study

1/2019

10/2019

No Value

Environmental

4/2019

7/2019

No Value

Design – Plans, Specifications and Estimates (PS&E)

4/2019

1/2020

Multi-phase

Construction

1/2020

9/2021

Multi-phase