ACTMTD Proposal: Greenville Automated (A-Taxi) Shuttles

Long Description for Task and Months Chart

Task Months
Task 1: Prepare detailed work plan Months 0 - 2
Task 2: Procurement of Vehicles Months 2-3, 8-9
Task 3: Field test vehicles Months 3 - 5, 9 - 11
Task 4: Analyze Need for Sensors Months 3 - 5, 9 - 11
Task 5: Pre-commercial operation Months 6 - 7
Task 6: Full Operation Months 6 - 36
Task 7: Mobility Center Months 3 - 12
Task 8: Data collection Months 6 - 36
Task 9: Reports and Outreach Months 9 - 36
Task 10: Final Report Months 30 - 36

Quarterly reports on the 3, 6, 9, 12, 15, 18, 21, 24, 27, 30, 33, 36 months.