Contra Costa Transportation Authority and Metropolitan Transportation Commission's: Innovate 680 Advanced Transportation and Congestion Management Technologies Deployment Initiative

3. Funding Description and Schedule

Private Sector Funding Source Contributions
Funding Sources
Non Federal Contribution Amount Contribution Type Committed/Pledged
Cash In Kind
CCTA/MTC $16,000,000 $16,000,000 $0 Committed
Bishop Ranch/ Sunset Dev. $1,300,000 $500,000 $800,000 Committed
Stantec $940,000 $160,000 $780,000 Committed
AAA $500,000 $250,000 $250,000 Pledged
First Group/First Transit $730,000 $125,000 $605,000 Committed
GoMentum $2,500,000 $2,500,000 $0 Committed
Telegra $1,000,000 $0 $1,000,000 Committed
Easy Mile $1,940,000 $140,000 $1,800,000 Committed
HERE $500,000 $0 $500,000 Pledged
Cisco $940,000 $0 $940,000 Pledged
Best Mile $200,000 $50,000 $150,000 Committed
Trafficcast $250,000 $125,000 $125,000 Pledged
Amber Mobility $200,000 $50,000 $150,000 Pledged
Total $27,000,000 $19,900,000 $7,100,000 No Value


Funding Plan by Strategy, Source and Year
Comprehensive Innovate I-680 Strategies Funding ($x 1000)
Year One
FY 18/19
Year Two
FY 19/20
Year Three
FY 20/21
Year Four
FY 21/22
Total
Enhance TDM Strategies
ATCMTD $ 375 $ 125 $ - $ - $ 500
In-Kind Contribution $ 1,125 $ 375 $ - $ - $ 1,500
Total $ 1,500 $ 500 No Value No Value $ 2,000
Provide FM/LM Connections
ATCMTD $ 267 $ 533 $ 200 $ - $ 1,000
In-Kind Contribution $ 733 $ 1,467 $ 550 $ - $ 2,750
Total $ 1,000 $ 2,000 $ 750 No Value $ 3,750
Innovative Operational Strategies
ATCMTD $ 910 $ 1,214 $ 3,034 $ 842 $ 6,000
In-Kind Contribution $ 2,390 $ 3,186 $ 7,966 $ 2,208 $ 15,750
Total $ 3,300 $ 4,400 $ 11,000 $ 3,050 $ 21,750
Prepare Corridor for the Future
ATCMTD $ 704 $ 900 $ 2,348 $ 548 $ 4,500
In-Kind Contribution $ 1,096 $ 1,400 $ 3,652 $ 852 $ 7,000
Total $ 1,800 $ 2,300 $ 6,000 $ 1,400 $ 11,500
ATCMTD Total $ 2,256 $ 2,772 $ 5,582 $ 1,390 $ 12,000
In-Kind Total $ 5,344 $ 6,428 $ 12,168 $ 3,060 $ 27,000
Total $ 7,600 $ 9,200 $ 17,750 $ 4,450 $ 39,000


Project Schedule by Program Element
Program Element Start Date End Date FY 18/19 FY 19/20 FY 20/21 FY 21/22 Deliverable
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Program Management
Project Management, Agreements 7/1/2018 6/30/2022 X X X X X X X X X X X X X X X X Meetings, budget, schedule, funding agreement, PMP
Environmental Clearance 7/1/2018 7/1/2019 X X X X                         Outreach Plan
Invoicing and Reporting 7/1/2018 6/30/2022 X X X X X X X X X X X X X X X X Monthly Invoicing and reporting
Enhance TDM Strategies
Outreach and Stakeholder Input 7/1/2008 12/1/2018 X X                             Outreach Plan
Develop Transportation App 10/1/2018 7/1/2009   X X X                         511 Corridor App
Shared Mobility Program 1/1/2019 7/1/2020     X X X X X X                 TNC & private sector agreements, bikeshare/carshare programs
Provide FM/LM Connections
Develop Implementation & Procurement Plan 7/1/2018 1/1/2019 X X                             SAV PMP, Procurement Plan
Procurement 3/1/2019 9/1/2019     X X X                       Procurement documents, procurement of vehicles and services
Integration and Testing 9/1/2019 7/1/2020           X X X                 Test plans, field testing of vehicles
Deployment and Validation 8/1/2020 8/1/2021                 X X X X         Operations and oversight of SAVs
Innovative Operational Strategies/Prepare Corridor for the future
Project Development 7/1/2018 12/1/2019 X X X X X X                     Concept of operations, interagency agreements, systems engineering
Procurement 12/1/2019 7/1/2021             X X X X X X         RFP/bin docs, contract award
Integration and Testing 8/1/2020 12/2021                 X X X X X X     Test plans, field test, acceptance
Deployment and Validation 1/1/2021 7/1/2022                     X X X X X X Expanded FSP, DSS, DSRC, ICM/ATM elements, Final Report