US 50 Integrated Corridor Management – Sacramento Region

13. Deployment Schedule

Table 8: US 50 ICM Project – Deployment Schedule for Segments 1 and 2
2017 2018 2019 2020 2021
1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half
MOU's, Charter No Value
Concept of Operations, System Requirements, Validation Plan, SEMP No Value
No Value Detailed Design No Value
No Value Corridor Preparation Infrastructure and Upgrades No Value
No Value AMS No Value
No Value ICM Component Development System Integration No Value
No Value System Validation and Acceptance No Value
No Value System Training and Begin Operations
No Value System Evaluation